Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

How to calculate the cement, sand quantity for plastering?
(10'x10')10mm thick ratio 1:5. wht"s the formula?

Answer Posted / rakesh kumar sinha

Total Plaster Qty.=.09cum
Cement 1cum=1440
Sand 1cum=1600
Ratio of cement and sand=1:5
so,
cement ratio=.02
sand ratio=.08
cement required
1440*.02=28.8kg
sand required
1600*.08=128kg

Is This Answer Correct ?    2 Yes 2 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Re: Can anybody help me by attaching files , formats for quality checks of common building materials like cement , concrete , bricks , sand and aggregates? please my email id is smgujjal@gmail.com

1997


What is min thickness,min grade of conc & age of PQC ?

9373


how to calculate quantity of bricks in circular manhole with examples.

5668


I am a civil engineer . I am also selected for sbi clerk interview which is to be held on 4th May2010 is there anybody resembling the same? what question can be asked and what should be the probable answers?

2369


Actually i am confused that how to calculate the bending moment for a semi-circular beam and curved slab.If any one have a good idea about the matter,please give the answer with a suitable example. Thank you......

2271


does a b.tech civil engineer fresher supposed to know how to design rcc structure?

3435


List out the potential risk factors for workers on the construction site?

1066


Iwant to calculate the production of 1 labour for concrete casting which includes shuttering,scaffolding,steel fixing,concreting, deshuttering and curing in 8hours.But i am not able to determine it approximately would you pls.??

2698


what is work of planning deptt. in any construction compny (in road project)

2436


how to find ssm in foundation?

1918


What is the different type of slump test indications?

1119


What is the difference between the concrete mix design carried out by IS10262 and by ACI method ?

2692


how to calculate the mortar for 10'*10' size room for both plastering and for masonry work?

1758


What is the development length given in pile?

2932


what do you understand by M25 concrete

2414