How to replace dia of bar in beam like 25mm 3no.S at bottom
But due to some reason on site 25mm bar is not available
Then is it ok to provide 20mm 4no.S? Give description or
Formula to calculate area of steel and replacement?
Answer Posted / iqbal
Due to some reasons required diameter of steel is not available then we required to compensate the availability of steel at site. i,e if 25 mm 3nos to 20mm the formula is
total area of 25mm steel X nos of rods Divided by area of 20mm dia of one rod
| Is This Answer Correct ? | 37 Yes | 0 No |
Post New Answer View All Answers
What is the veriplus for ellips card length formula (major axis 3.4m,minar axis 2.6m spacing 0.2m
I'm preparing to to build a simple house, but i don't know how to calculate how much cement, gravel and sand and hollow blocks i need to prepare. How many pcs of 4" or 6" hollow blocks I need for my planned 3mx6m house? thanks.
what is the types of door's wood?
Define What is a kip?
what is mail role & relationship between senior Civil engineer to consultants , Construction manager ,project manager, project engineer ,Technical engineer & qa/qc engineer ? what is the responsibilites of Senior Civil Engineer?
Why was the empire state building made of steel?
What is Gsb tollens ?
How much area, in square meters, will one liter of paint cover if it is brushed out to uniform thickness of 600 microns?
how many BSCs can i connect to the HUAWEI MSC
how do you calculate the length of "L" of main & distribution bar for reinforcing of raft footing
Which is stronger solid steel rod or hollow steel pipe?
What is semirigid connections?
With reference to construction of state highways, please let me know the total Bill Of Quantities as per the following details:- 1) Subgrade - 500 mm 2) Granular Sub-Base (GSB) - 200 mm 3) Wet Mix Macadam I (WMM I) - 150 mm 4) Wet Mix Macadam II (WMM II) - 100 mm 5) Dense Bituminous Macadam (DBM) - 60 mm 6) Bituminous Crust (BC) - 40 mm Road Length is 44 Kms. Road Width is 7 mtrs. Please provide the BOQ of each layer as per Compacted Factor & Loose Factor both. Also, if possible please provide me the approximate details of total material required (all categories viz. soil, gravel, stone aggregrate, sand, bitumen etc.) as per general mix design prevailing in India. Thanks & Regards -- Rokr
How much form and scaffolding per cubic meter volume of concrete class ''A'', ''B'', and ''C''
What is the sugested procedure of water purification for public supply?