how the calculatio is taken for shuttering in staircase.
Answer Posted / m.senthilkumar
1.(FLIGHT & LANDING) calculate each flight underside,landing
underside area.landing underside area is normal L*B,but
flight underside area calculate using formula (A*A +
B*B=C*C)=length of flight then L*B=AREA .
2.(WASTE SLAB) calculate waste slab side ex.waste slab
thickness0.150m
flight length 3.8m=(both sides)2*3.8*.15=1.14sq.m.
3.landing sides=l*h(l=3sides)
4.(STEP) ex.width of staircase=1.25m,riser=.15m,threader.3m
each flight13steps
each flight calculation=width=1.25*13=16.25sq.m
both sides =(0.15*.03*13)=0.585 sq.m
because((.15*.3)/2*2=0.15*.3)OK.
Is This Answer Correct ? | 6 Yes | 19 No |
Post New Answer View All Answers
need to join coaching institute in coimbatore tamilnadu ......say me the best coaching for IAS
what is the specific gravity of rubble in plum concert
how can calculate the compressive strength of concrete cylinder by water cement ratio ?
CAN WORK WELL UNDER DEAD LINES OR PRESSURE?
Can any body help me out by telling hoe swelling pressure test of soil is carried out ? some body told me the procedure & formula (change in length /116.3*100%) but still i am confused ? pls help.
What are the composition of a landfill?
Which code specifies the specification ofthe construction joints to be provided in the raft slab of a basement which is 6 m deep.what should bethe detail of such a joint?
What is the standard unit weight of Cast Iron pipe of 200MM Dia.(pipe specification is IS1538)
What are the advantages and disadvantages of using plastic and timber fenders?
why we use 19x9x9and 20x10x10 but not other
which red: used in roof teping, then use only cement
how to preaper for interview wat they asked in interview give me idea
what motivates you to do a good job
Define the various stages of the project planning process in construction.
What is the life of anaerobic Digester if it is used for municipal solid waste digetion.