1 Cum Brick Work CM 1: 6 - How Many Bricks ,sand,Cement
Required? Brick Size 9" 4.5" 3"
Answer Posted / er.harjinder singh
Exp:-length of wall=10ft
Bredth of wall=4.5in
Height of wall=9.5ft
Qty.10*0.375*9.5=35.625cft
Provide .5in morter in each line of bricks.
So,first calculate qty.of mortar in total work with following steps:-
Step-1. Calcuate qty. of mortar in one line
of bricks:-
10*0.375*0.0625=0.2344cft.
Step-2. Calculate nos. of lines of bricks in given height:-
9.5/0.292=32.53 or 33bricks.
Step-3. Calculate qty. of mortar:-
33*0.2344=7.73cft.
So,Total brick work:-
35.625-7.73=27.895cft
Net. Qty. of bricks=
27.895/0.0703=396.8bricks
say 397 bricks
Is This Answer Correct ? | 31 Yes | 28 No |
Post New Answer View All Answers
How to calculate density of 40 mm coarse aggregate, in mixing ration 1:1.5:3? Please explain calculation for density
how to nfind out the specific gravity of sand.aggregate,water please help...
it is a corrected question." make a list of engineering property(properties) of soil.
how many numbers of 4inch bricks and get consumed in 9 inch BB masonary wall in cubic feet.plz send my below e.mail adress
in one SQM plaster how much Cement and sand consumed in ratio 1:4
Design a cantilever slab to carry a live load of 2000 N/m2. The overhang of the slab is 1.20m. b) A slab over a room is 4.75m x 4.75m. The edges of the slab are simply supported and the corners are not held down. The live load an the slab is 300 Kg/m2. The slab has a bearing of 15cm. On the supporting walls. Design the slab as per Rankine - Grashoff theory. Assume weight of R.C.C. = 2400 Kg/m2.
Can a wave happen in the middle of the ocean like in the movie poseidon 2006?
How to calculate cement, water, fly ash amount for 1 cum if the w/c ratio is 0.4 and fly ash to cement ratio is 1:9
Kindly post me previous year interview questions with answer for post of DY. Manager (civil engg.) for GAIL, NTPC, IOC, OIL and ONGC etc.
what is Short bored pile foundation.
Define different types of roof systems?
Which is the indian standard code of line out. ? How much tolerance fot 1 mt lenght? Its challenge....
rate analysis hiring of generator 62.5 KVA
give me the mix proportion for design mix concrete M 7.5 grade 1:4:8
what is the difference between np2 and np3 concrete mix