My ups output shows 230 v between phase and neutral,but show
zero between phase and earth.Is the system/installation is
correct.If not what will be the possible reasons
Answer Posted / hemalatha
earthing point where you checked may not be perfect.
| Is This Answer Correct ? | 6 Yes | 4 No |
Post New Answer View All Answers
i have a 1500kVA transformer what is the kWH meter i need to use?
what is formula to cal cute earth pit numbers and size of earth strip used in earthing?
we have two motors 1250kW,6.6kV to be coupled on the same shaft ,so please provide assistance for their synchronisation.
How CFL &T5 tube light glows?
to vary valtage from 0 - max a variac is necessary . so how to design for high power applications nearly about 200KW power
Why an ac solenoid valve attract the plunger even though we interchanges the terminal? Will the poles changes?
Has someone here done a sizing for a generator (3 phase), its for a pumping station. If you have an example for standby/duty and both running (I) star delta (ii) Soft Starter.
how indusrial diesel generator work
what are the ''pitting rings''and how cn they be controlled in a series generator
how can we make cable shedule for controll wiring ? which details must be required for it.?
When we use air circuit breaker, it has O/L protection ,time delay SC protection, Instataneous SC protection & ground fault protection. They all have some setting range. But what is the suitable/allowable setting for the above protection which will be safe for the equipment? For example-O/L protection setting have a range of (0.4,0.45,0.5,0.55,0.6,0.65,0.7,0.8,0.9,1.0)xIn Time delay SC protection have a range of (1.25,1.5,2,3,4,6,8,10,12)xIn Time delay setting is 0.02,0.1,0.2,0.3,0.4 Instataneous setting is fixed to 20xIn Gound fault setting is given 100A,300A,600A,900A,1200A This setting are for 2500A ACB. So what will be the basic allowable setting for the above protection? is there any formulae to calculate this<
IN electrical field, WHAT ALL THINGS THE CUSTOMER WILL ASK WHILE ORDERING FOR LT PANEL (ALL TYPES OF LOW TENSION PANEL)
What is mean by hot and cold loop testing? What is the difference between them?
i have total 8 dg sets for synchronizing and 2 buscoupler,1 sectoin dg no 1,2,3,and 2 sectoin dg no 4,5,6,and last section dg no 7,8 ....if buscupler no 1 and 2 is off mode ..than dg no 1,2,3,will synchroniz of another dg sets?
what is the easiest method of short circuit current calculation ? pls. derive with a mathematical example in real life application.