how many cement use for 1cum concrete for 25Grade.

Answer Posted / pramod abhimannue

Dry Volume for 1 Cum Mix is 1.54 Cum.

Ratio for M25 is 1:1:2 = 1+1+2 = 4

1 Part of cement would be = 1.54/4 = 0.385 cum.

1 bag of cement = .035 cum

total bag of cement = 0.385/.035 = 11 bags

1 bag of cement = 50 kg of cement

11 bags = 50 x 11 = 550 kg of cement

cement required for 1 cum of m25 grade concrete is 550 kg.

Is This Answer Correct ?    81 Yes 20 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What are the basic use of runners and standards of pipelines?

674


How many cement sand ballast in cc 1:4:8 40mm

1534


i have applied 40mm spacer in the concrete for tie beam. is it correct? kindly give me if there any code available

1442


How cracks in concrete can be avoided?

639


how much st. steel is required for staging of concourse slab of a elevated metro station allowing through traffic .

2259






Method of findingthe dry ingredient quantity of 1 m3 concrete. what is the difference between static and dynamic induced emf? Testing charges bill given for Rs. 32,000/- but not added service tax in this bill. So, How much TDS will be deduct

1017


for 16mm thick cement plastring 1:6 on 100 Sq.m.New brick work,the quantity of cement required is.

1512


What is a hatch patterns?

669


can you mail me detailed procedure,entire syllabus and practice papers of mpsc civil engineering branch.I am in third year now

1661


What tor stands for in tor steel?

625


what should be RCC material i.e iron rod(mm)x cement x stone x sand for laying of slab L 42'x B 22'x tk 0.375ft = 1nos & column of H 17'x15"x8" 2nos.

1889


how many monpower required for 1 sqm normal RCC structure ( includes finishes & MEP )

2216


Wats the formula of eccentric footing and how was calculated from concrete qty

2559


will fix foundation bolts at site with out template is there any procedure?

2155


What Are The Steps Involved In The Concreting Process, Explain?

824