Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

how many labour is required for 1cum of concrete?

Answer Posted / sathesh.b.nama

3CUM/DAY/ MASON WITH 1 HELPER CAN DO RCC & 5CUM/DAY/MASON WITH 1 HELPER CAN DO PCC..IS NORMAL PRODUCTIVE NORMS OFA A MASON NOW-A-DAYS

Is This Answer Correct ?    12 Yes 6 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

suppose that  156000 sq.ft rcc work builtup are.how many % of brick work to rcc work.

2769


please what are the required bars for a beams of 6mx6m and 450x300mm, one is continuous and the the second is discontinuous ..Its a commercial building (church)

1875


why the openings of sieves are square io size?

1669


How to calculate paint drums per meter square

2620


60-70 grade of Bitumen is VG-30 ?

2179


What is change order request?

1161


Explain what is change order request?

1193


How to calculate the area of a irregular sized land in square feet?and what will be the total area of this land South-51.1ft , North-47.7ft , East-53.3ft , West-54ft ?please explain me how to calculate?

2065


Will water damage concrete?

1370


what is relation between SPT N value and driving piles after conducting a soil test?

2259


Difference between pre-tensioning and post-tensioning.

1227


how i get all type of short type question answer about civil engg

1765


What is meaning of FREE STANDING STAIRCASE ?

3094


is there any codal provision for soil cousion over the Hume pipe of Dia 1.2 m.

2187


How much form and scaffolding per cubic meter volume of concrete class ''A'', ''B'', and ''C''

2216