URGENT PLEASE//////////A WORK SHOP IS HAVING A 100 KVA
TRANSFORMER 11KV/415 VOLTS,
AND THE CONNECTED LOAD OF THE WORK SHOP IS 80 KW WITH
INDUCTIVE LOADS, LIGHTING LOADS,ETC.,
HOW MANY EARTH ELECTRODES ARE NEEDED AND WHAT IS THE EARTH
RESISTANCE OF EACH EARTH ELECTRODE AND COMBINED EARTH
RESISTANCE in normal soil. AT 11 KV SIDE AND AT LT SIDE. HOW
TO CALCULATE.
Answer Posted / sudhakar g
For any transformer it is better to install two for body
eathing and two for Neutal earthing
Body Earthing: GI pipe 40mm dia using charcoal and salt
like this
Neutral Earthing: Copper plate 600x600x3 mm size for
netural earthing with all neccesary materials
After completion of Earthing you need to check the earth
resistance value for these earthing it should be below 3ohms
I think these are the neccasary requiremnts for your
trasnformer
According to IS standards the distance between pits must be
2.5mtrs and from the building it should be far from 3000mm
I am taking Electrical desining classes in Bangalore...It
will be usefull for designing as well as site engineers
those who are intrested to go for Electrical
Engineers....we give you indepth knowledge of Load calu,
Cable sizing, Lighting cal, panels, breaker
selection,Autocad drawing....if any body intrested means
pls call to +91-7760362623 or sudhakar28485@gmail.com
| Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
What is bridge rectifier and explain with details
i need of the bhel question papers along with answers and also give some website names for the downloading question (electrical and electronics engg question)please help me....
WHAT IS SITTING AMPS IN OVER-LOAD RELAY FOR 1PH OR 3PH MOTORS?IF ITS NAME PLATE GIVEN MAX AMPS 10AMPS?
What is vacuum circuit breaker.define with cause and where be use it device?
How isolater function when installed inelectrical 440V wiring
A 15 kw squirrel cage motor having a maximum efficiency of 90% on a continuous full load has temperature rise of 42 degrees celcius after 30 min and 52 degrees celcius after 1 hr under the above operation conditions. a) calculate its final steady state temperature rise on continuous load and the heating time constatnt. b) if the motor is operated on a short load for 9 min estimate its temperature rise. c) calculate the maximum overload that can be applied on a short, 9 min rating so that the temperature rise is the same as the final steady state temperature rise on continuous load.
give single line diagram of D.G distribution form alternator to main L.T panel?
If a 3 phase induction motor is in off condition in the conveyor and rotor of the motor keeps moving with the conveyor than the resistance of windings of motor varies. why is it so ??
which types of relay used in acb and vcb?
explain all the classes with example
WHY EXCITER PHASE SEQUENCE ARE OPPOSITE THAN STATOR SUPPLY PHASE SEQUENCE IN SYNCHRONOUS MOTOR >
what is the principle of operation of tungstun bulb ??
What is the difference IN MCCB's between thermal magnetic and electronic tripping system ?
I HAVE A 50A MCCB AS PER DESIGN LINE WIRE CONNECT UPWORD SIDE AND LOAD IS CONNECTED TO DOWNWARD SIDE TO THE MCCB.IF NOW ANY ONE CHANGE SUPPLY & LOAD(WISEVERSA) WHAT HAPPENS ? DOES MCCB OPERATION OR WORKING FUNCTION NORMAL IF YES THAN WHY THERE ARE MARKED LINE & LOAD ON MCCB.
if a.c supply is given to the motor,, what happen?