calculation of cement bags in 1:2:4 concrete mix
Answer Posted / shinu
For 1 m3 of concrete (1:2:4)
Required volume of concrete=1.00
Add 35% extra for additional voids in concrete ie 1.35
Therefore Total qty=1.35Cum
Total Mix=1+2+4=7
Therefore Quantity of cement =1.35/7= 0.193Cum
Qty of Cement in Kgs = (0.193*1440)=277.92 Kgs
In Bags, 277.92kg/50kg=5.56 bags
otherwise
1cum Cement=1440Kgs ie 28.8 bags
In Bags 28.8*.193=5.56
| Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
What is the number of IS code of practice to be followed for hydraulic design of sewerage pipe line?
What is the difference between shear and tensile strength?
What is a projection line?
can any one explain bar bending schedule of bems and columns and slabs ??
What applicable rate of wct in bihar
How to Know that veriation acceptable in CPWD Work Of 1:6 Cement Mortor Received Lab test report.
what is the productivity in aluminium shuttering per day
how much cement and sand required for 100sqm of wall plastering in different proportions
what is raft foundation
whats is difference between anchorage length and development length
How much cement will require for 1Rmt Skirting laying
What is the amount of work done by a carpenter, bar Bender and plaster Mason in interior and exterior plaster
at what pressure ply-wood is obtained by gluing wooden sheets
What do you mean by the word 'shear'?
In an aggregate blending plant, water is sprayed before blending is performed. If the fine content in aggregate is as high as 25 %, will not the fines form into lumps / balls and distribution will not be uniform ? Further, the fines will stick onto the interior of pug mill and its content will be low. The mixed material is stockpiled for weeks / months before use. Will it not be better that blending is done in dry condition, and water will be added only during compaction at site. Please forward your comments and suggestions.