how to calculate 1:2:4 ratio concrete cement, sand, metal
and water please give me brief calculation
Answer Posted / mavani hitesh
for mixing of 1:2:4 proportion
1 is stand for cement, 2 stand for sand and 4 stand for aggregate.
for volume batching.standard pharma is used.which is of 35 liter.
for 1 bag proportion.
cement= 1 bag
sand= 2*35
= 70 liter
aggregate= 4*35
= 140 liter
in cum
1 cum = 1000 liter
70+140=210 liter
reduce 25% of 210 for wet mixed.
which comes 158 liter
1000 liter/158 = 6.36 bag of cement
| Is This Answer Correct ? | 19 Yes | 7 No |
Post New Answer View All Answers
manhole chamber having height of 2300 mm and thickness of brickwork is 230 mm and dia of opening covering is 560 mm and bottom length vertical is 1500 mm (1:4) brick masonry and plaster 12 mm on both sides..how to estimate the no bricks used with mortar cement bags and sand for total chamber including plaster.
Explain what is Hybrid Foundation?
how to calculate the material from ratio of work PCC, RRM,POINTING, RCC
what is the anchorage length of reinforcement.
may i know the detailed description of cutting length
A rock anchor 3 1/2” in diameter is placed in rock. The which has an allowable shear strength of 1200 psi. Determine the required anchorage length to safely carry a 80 ton load using a 2.0:1 F.S
how much shouid be the rate for ready mix concrete per cubic meter
For 1 bag cement how i will calculate sand and metal aggregate;Here the mix proportion is 1:2.49:2.38
difference between trapezoidal and pedestal footing and how the load acts on that
what are the code used for residental building?
what is labour consume factor in residential projects
What is the amount of work done by a carpenter, bar Bender and plaster Mason in interior and exterior plaster
how to nfind out the specific gravity of sand.aggregate,water please help...
RR masonry rate analysis
Why we provide hair pin for shed