Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

for preparing 10cum of 1:4:8 cement concrete the
requirement of sand is
0.7cum
2.8cum
4.74cum
18.40cum




& how

Answer Posted / engr.asad ali

we know that
Total wet volume of concrete = 10Cu.m
First we find dry volume
Dry volume = wet volume X 1.54
Dry volume = 10 X 1.54 = 15.4Cu.m
Determine sum of ratio = 1+4+8 = 13
And also we know that
Quantity of Sand = ration of sand X wet volume
-------------------------------
Sum of ratio
Quantity of sand = 4 X 15.4
-----------
13
Quantity of Sand = 4.738 Cu.m say 4.74Cu.m

Is This Answer Correct ?    71 Yes 4 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

how much one carpenter can doing shuttering of slab in one day

3344


Explain moment of inertia?

1121


How do you compute the volume of airflow?

1114


what is the use if we fixed butterfly ties in column and masonry work joint?....where we have to fix(distance)..

2509


What do you meant by gui?

1242


How do you compute volume of airflow?

1309


Trapezoidal section footing calculation of Volume & its Area

36295


How to improve the strength of fly ash bricks to avoid corner damge? How to get the color lighter similar to normal concrete blocks/

1869


how to take the quantity of block work and plastering  1block price:3saudi riyal cement:1bag:15 saudi riyal sand:3bag:20 saudi riyal 1mason:9hour per hour 40 saudi riyal 1labour:9hour per hour 40 saudi riyal can anybdy calculate

2470


about higyway engineering

4429


List out some of the software used in the construction sector to estimate cost and monitoring expenses?

1148


How much permissible bearing capacity requires for open footings(isolated) and what type pile foundatuon prefering for coastal areas?

1992


explain what do you mean by the property development.

2098


Dear Sir, I work in hydro project. I want to hire Scorpio/ Bolero on monthly basis. But how can i justified its amount (Hourly basic). Please solve my problem

2757


what is escalation?how it is done?

2517