How to calculate the cement, sand quantity for plastering?
(10'x10')10mm thick ratio 1:5. wht"s the formula?
Answer Posted / risadh
Formula=Volume*Density of material
Add- Shirinkage-35%to40%
Volume= plastering volume+Depression,joint&Wastage
Density=Cement-1440Kg/m3,Sand-1600Kg/m3
Shirinkage-35%to40%
Depression,joints&Wastage normally-20%of plastering Volume
Cement=(1/6*0.11124*1440)+(1/6*0.11124*1440)35%=
Sand=(5/6*0.11124*1600)+(5/6*0.11124*1600)35%=
| Is This Answer Correct ? | 1 Yes | 2 No |
Post New Answer View All Answers
what might be the problem faced in the near future if the M-sand is used in the place of river sand during wall plastering? (As per IS)
How can calculate the requirement of steel bars of rcc slab for 1100 sq ft?
What is the Maximum %age of Steel in columns and beams ?
What is the difference between Fe 500, Fe 500 D and Fe 515.
What are the different methods for drawing an arc?
How to calculate woden area in sft and Cft
Which percentage of carpet area use in plot area of office building.
the water is flowing through a velocity of 1.5m/s in a pipe of length 2500m and dia 500mm. at the end of pipe a valve is provided. find rise in pressure 1. if the valve is closed in 5 seconds. 2. if the valve is closed instantaneously. take value of c = 1460m/s, pipe to be rigid and bulk modulus of water - 19.692x10' n/sqcm
how many shuttering material required for 1000 sq.m built up area.
asubmerged weir is one in which the water level on the down stream side of the weir is just at the crest level below the crest level above the crest level at stamp elevation as water surface on upstream
what is the list of building construction equipment & teir output?
How much is the cover for slab?
acceptance criteria for concrete works
In jack arch floor, the rise is kept?
Which code specifies the specification ofthe construction joints to be provided in the raft slab of a basement which is 6 m deep.what should bethe detail of such a joint?