How to calculate the cement, sand quantity for plastering?
(10'x10')10mm thick ratio 1:5. wht"s the formula?
Answer Posted / risadh
Formula=Volume*Density of material
Add- Shirinkage-35%to40%
Volume= plastering volume+Depression,joint&Wastage
Density=Cement-1440Kg/m3,Sand-1600Kg/m3
Shirinkage-35%to40%
Depression,joints&Wastage normally-20%of plastering Volume
Cement=(1/6*0.11124*1440)+(1/6*0.11124*1440)35%=
Sand=(5/6*0.11124*1600)+(5/6*0.11124*1600)35%=
| Is This Answer Correct ? | 1 Yes | 2 No |
Post New Answer View All Answers
Is it possible to make a feature using an overdefined sketch?
What is meant by cad?
How much qty of stone ; sand; cement in R/R stone masonry of 136 CUM
i have span of 6m x 4m how do i calculate the reinforcement of steel i needed and to at what distance and also the thickness of slab. looking forward thank you RAVI
What Reinforcements Are Used In The Process Of Prestressing?
What is 1/8 on the architect ruler denotes?
What is the difference between yeild strength and compressive strength of steel???
Q 1) 1 Mason and 2 LABOUR / _________CUM brick work Q 2) 1 Mason and 1 LABOUR / _________SQ FT Plaster work Q 3) 1 Carpenter & 2 Labour/_________SQ FT shuttering work Q 4) 100 SQ FT roof slab concreting ____________mason and labour required
How to increase a bearing capacity of soil?
I want to know the material required per Square foot in rcc roof i.e.Steel ,Cement,
how clculate excavated or backfilling quantity by simpson's rule
What are advancements in civil engineering?
for pretensioning which will yield first and same for post tensioning?
1)Why we can use half brick in 4inch wall and 2)why not in 9+inch brick wall
A roof has a U value = 0.65 W/m2 .C. Extra insulation is to be provided. This insulation has a thermal resistance = 1.5 m2"C/W. Calculate the new improved U value.