How to calculate the cement, sand quantity for plastering?
(10'x10')10mm thick ratio 1:5. wht"s the formula?
Answer Posted / risadh
Formula=Volume*Density of material
Add- Shirinkage-35%to40%
Volume= plastering volume+Depression,joint&Wastage
Density=Cement-1440Kg/m3,Sand-1600Kg/m3
Shirinkage-35%to40%
Depression,joints&Wastage normally-20%of plastering Volume
Cement=(1/6*0.11124*1440)+(1/6*0.11124*1440)35%=
Sand=(5/6*0.11124*1600)+(5/6*0.11124*1600)35%=
| Is This Answer Correct ? | 1 Yes | 2 No |
Post New Answer View All Answers
How many % we consider for lap for reinforcement for estimates
What is the tensile strength of marble?
What is an ice dam sock?
Explain what is alternate bid?
how statics is different from dynamics
Explain how you can use different dimension tools in CAD? What are the different dimensions available?
Spider cracks occur in beam bottom due to––
how to identify np3 pipe and np4 pipe
TO CONSTRUCT A 1800 SQFT CAPACITY UNDERGROUND WATER TANK HOW MUCH CUFT CONCRETE IS REQUIRED AND HOW MUCH REINFORCEMENT IS REQUIRED. FOR COSTING
What is difference between engineering stress and true stress?
while doing the structural works of a simple ground+1 villa, can the columns be continued immediately after neck columns without tie beam, while the tie beam to be done after columns concreting.
if we use 1.25 bag of cement 3 pharma metal and 2 pharma crush sand what is the strenghtexpected for RCC column
what is mail role & relationship between senior Civil engineer to consultants , Construction manager ,project manager, project engineer ,Technical engineer & qa/qc engineer ? what is the responsibilites of Senior Civil Engineer?
Sometimes the side of concrete bridges is observed to turn black in color. What is the reason for this phenomenon?
What is portland cement