Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

What is the process of project flow n sap?In context to
project flow what are the role of an abapper?

Answer Posted / babu

The implementation of your SAP System covers the following
phases:
1. Project Preparation
In this phase you plan your project and lay the foundations
for successful implementation. It is at this stage that you
make the strategic decisions crucial to your project:
o Define your project goals and objectives
o Clarify the scope of your implementation
o Define your project schedule, budget plan, and
implementation sequence
o Establish the project organization and relevant committees
and assign resources
2. Business Blueprint
In this phase you create a blueprint using the Question &
Answer database (Q&Adb), which documents your enterprise’s
requirements and establishes how your business processes and
organizational structure are to be represented in the SAP
System. You also refine the original project goals and
objectives and revise the overall project schedule in this
phase.
3. Realization
In this phase, you configure the requirements contained in
the Business Blueprint. Baseline configuration (major scope)
is followed by final configuration (remaining scope), which
can consist of up to four cycles. Other key focal areas of
this phase are conducting integration tests and drawing up
end user documentation.
4. Final Preparation
In this phase you complete your preparations, including
testing, end user training, system management, and cutover
activities. You also need to resolve all open issues in this
phase. At this stage you need to ensure that all the
prerequisites for your system to go live have been fulfilled.
5. Go Live & Support
In this phase you move from a pre-production environment to
the live system. The most important elements include setting
up production support, monitoring system transactions, and
optimizing overall system performance.

Is This Answer Correct ?    4 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What are the major steps will you use for tuning?

1062


Did you create secondary index?

1159


What is the difference between data elements and domains?

1114


What are the two different ways of building a match code object?

1040


Explain the table, which contain the details of all the name of the programs and forms?

978


What are the different types of luws?

1182


What is the use of table maintenance allowed?

1068


What are the two levels in defining a match code? : abap data dictionary

1124


Can we define our own match code id's for sap matchcodes? : abap data dictionary

1040


How to select valid lines for secondary list?

1080


What are the differences between primary and secondary indexes?

1240


Name the abap/4 modularization techniques? : abap modularization

1079


What are the differences between transparent tables, pooled tables & cluster tables? : abap data dictionary

1214


How to eliminate duplicate entries in internal tables? : abap data dictionary

1298


How to combine multiple billing into one RV document ( Step by Step)?

1973