Answer Posted / azeem
maximum demand is the product of connected load and the diversity factor.
if a plant is having a motor assembly of 200 kw connected load
than the maximum demand will be(200 kw * 0.85 diversity factor)= 170 Kw for time interval
| Is This Answer Correct ? | 3 Yes | 0 No |
Post New Answer View All Answers
What is different between Difnit time and instatous over current relay
how to find 5 kilo meter long under ground 33 kv cable fault location if IR VALUE shows 0.05 M ohm @5000 volt.and cable fault locator shows some time fault distance 3 kilo meter ,3.7 kilo meter and some time 1 kilo meter? now how to find the fault location that where is leakage. note--it is tested with 5000 kv megger and insulation resistance is 0.05 M ohm. and some time 0.03 M ohm comes.
what are the applications of PLC?
When we have earthing mesh or underground earthing network in industrial plants, weather we have NT-S or NT-C-S kind of earthing system, so eventually weather we must use 4 or 5 wire in 400 volt level (For example 3×150+70 mm2 or 5×150 mm2) in this connection I would like to know exactly the paragraph of IEC or IEEE number
im electrical engineer, could any one help me for FEWA exam questions please ?
Please, if 1kw is equal to 1.25kva; how then do I know how many kva in 7.5kw?
When color of silica gel will gets change from blue to pink from Top to bottom?
I am a electrical engg. diploma holder,applied for junior engineer (electrical),Kolkata RRB. Have I to attend all electrical,mechanical&civil portion in written exam.???
how to calculate micom relay earth falt time and current sertting
USE OF 8 WAY PAN ASSEMBLY
DESCRIBE THE CONSTRUCTION ANDOPERATION OF BELT CONVEYORS AND SCR CONVEYORS , DRAW NEAT SKETCHES
sir please send me techinical questions for junior engineer posting in bangalore railway i am diploma holder
How Self works in DG set
what is the function of bearing in dc mchine" and where it is placed
why we use the 100% and 95% stator earth fault protection for the synchronus generator ?