IF THE OUTPUT OF A 100KVA, 415V GENERATOR IS STEPPED UP TO
11KV WITH A 500KVA TRANSFORMER,CAN THE TRANSFORMER BE
LOADED ABOVE THE SOURCE GENERATOR RATING?
Answer Posted / ben
firstly a 100kVA 3-phase WYE generator will only produce 100kVA of power, this will also more than likely be rated at 0.8 power factor meaning the true power you will receive will only be 80kW.
if you are using a 500kVA, 415V/11000V step-up transformer you will probably find that the 100kVA generator is not large enough to saturate the transformers magnetisation current. i would have to say you need either a larger generator or a smaller transformer to suit your site needs.
In answer to your questions: No it can not.
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
how to discharge 3 phase power factor correction capacitors
what is the method of earthing of a transformer using electrodes?
I need to connect a synchronous generator to the grid using automatic synchronization and two circuit breakers (one for synchronization, one for end connection to the grid), how to determinate the required diameter of the cables?
STATE USE OF ARC RUNNERS & SPLITTERS ?
how we do Vector group ,magnetic balance and tap changer test in Transformer?
We have two APFC panels in same station. I need how to connect CT in two APFC panels.can we take one CT in series connection or two separate CTs.
State how to produce a constant rotating field by application of alternating currents to stator armature of a three-phase squirrel-cage induction motor
Write the force balance equation of ideal dashpot element.
What is the formula to calculate the size of Aluminium and copper cable?
Difference between megger test equipment and contact resistance meter test instruments?
What are the types of control system?
can anyone tell me can the electromagnetic waves can be reflected back?if so how &by which material it can be reflected back?please tell me so that it can help to my wireless power trasnmission device.
I am getting above 60 V as open delta voltage against single phase unit ICT at tertiary delta formed and ICT getting trippped on NDR. ICT tested and found in order. PTs provided on tertiary are tested and in order. what may be the reason?
Pl. give me checklist for installation & commissioning of machine tool.
what is servo motor & how does it work.