why we provide plastic sheet under lean concrete/pcc.?
Answer Posted / muthukumar
Firstly your question is not specfic any how we have
certain minimum standards to follow as per standard.
1.Usually incase of Concrete screed (Floors) laid above the
plastic sheet beacuse to prevent the concrete in direct
contact with soil which may have some active chemical will
directly react with concrete and alter its property.
2.Specially at foundation where the capillary rise of water
is there plastic sheet or layer sand is used to reduce the
capillary rise of water into the structure
| Is This Answer Correct ? | 35 Yes | 3 No |
Post New Answer View All Answers
why we create short columns under grade slab?
Please send me the qunty. of mason/labour required in each day for different type of civil construction work?please send me ans. in my mail.my mail id is (parthamitra086@gmail.com) or here.
questions with answers to face an interview of an civil engineer regarding RCC buidings
Define What glue is least sticky?
Process of pcc in wateredug
Formula for calculation volume of essentric footing
What is the software used in civil engineering?
What do you mean by the word 'shear'?
what is the water cement ratio for plastering
What is M40 _ TOR - EQ and B.F.S
What is thumb rule for deep trench excavation
How do you compute moisture correction using the parameters gathered from Nuclear Density Gauge Apparatus and the moisture contents results from the lab.?
What happens to Load at yielding ?
cause of cylinder test failure
20mm thick sand face plaster on walls consisting of 12 mm the backing coat of c.m.(1:3)and 8mm thick finished coat of c.m.(1:1)including scaffolding, watering, finishing etc complete please calculator with methyl et et r u