What is the difference between Type test and Routine test?
Answer Posted / hhhhhh
Type test:
It is conducted on first prototype of product to confirm
the design specifications.This test is not repeated on
other products of same type.e.g, temp rise test
Routine test:
It is conducted on each product manufactured to confirm
proper maufacturing of each and every units.This test is
essential to be performed on each unit before distaching
the product to site.
| Is This Answer Correct ? | 5 Yes | 7 No |
Post New Answer View All Answers
I have 4 DG set with 1500KVA rating. system breakers are 11KV & alternator are 415 Volts. Between alternator & breaker one stepup transformer used. i want to Know what is max. resistance for body earthing & 415 & 11KV V Neuteal earthing. my fault current is 14 times for 2 sec.
how much GROUND & NEUTRAL VOLT maintain in data center.
If there is major % of Voltage harmonics in the system, how can it be control or reduced?
What is resolution of a measurement?
What is float cum boost charging system?
how to select overload-relay for perticular motor 1.for D.O.L. starter 2. for Star-delta starter ????
block diagram of 2 ups system connected in hot stand by mode?
If i have two 3000 kW motors and the whole facility requires a 10 MVA transformer. What would be better installing two 5 MVA transformers(one for 1 motor ) or just a single 10 MVA transformer for both of them. Give reasons for your answer.
What are the factors which influence the choice of specific magnetic and electric loadings of a synchronous machine?
which phase is preferred for connecting 1 phase vt used for synchronizing OHL? WHY?
what is the efficiency of thyristor
While testing LA mast,What are the parameter limits ?
i have been tasked with a design of protection, metering and control(PMC) relay panel extension to accommodate all PMC relays.There is an already existing panel where this one will be built.What are the design aspects for this kind of project? thank you.
how we control automatic generator i'e with to supply (main supply and local generator) when the main supply was break to supply the local supply automatically to begin supplying power.I now this control circuit is the combination of contactor time delay contactor switch and overload relay .but my question is how we combine those component thank you
What is the difference between line drop and percentage line drop?