how many bags of cement required in neat cement finish per
square metre
Answer Posted / kumar
above answer is wrong. simply
for one Sqm of neat Cement Finish With 15 mm thick plaster -
0.145 Bags of Cement Required For Sqm.
Calculation = 0.145 * 290=42.05
Sand = 0.015*1260 = 18.9
total Material Cost = 60.95
Labour Cost is = 90 / SQm
So all together = 150.95 Say 150.
from ur calculation
for one Sqm = 32.5 kg of cement
that means = 32.5 X (290/50)= 188.5 / Sqm
is it Any boq Neat Finish gave above 300/
| Is This Answer Correct ? | 4 Yes | 19 No |
Post New Answer View All Answers
How many pyramid in egypt?
How many litres of water used for curing of 1000sqft of slav
what is the use if we fixed butterfly ties in column and masonry work joint?....where we have to fix(distance)..
What is the different type of slump test indications?
Define different types of roof systems?
Can we use Polystyrene as a Bitumen modifier !! if so is it a good MS research topic ? and what type of laboratory tests will be conducted during Research work ??
How to estimate the shuttering material requirement for a slab and beam and shear wall..? Please send thumbrule to estimate material required ( Plywood, Ms plates, runners, acrospans, jacks)
What are the methods in tiles flooring ? What are the methods in brick work? What are the methods in plastering ? What are the methods in wall tiling?
How much form and scaffolding per cubic meter volume of concrete class ''A'', ''B'', and ''C''
I was once rejected for US visa in early August. But now I'm going again for interview next week. What are the chances that I will faced the same VO????
If we are providing concrete joint in every 10m with water stopper in water tank wall then is it necessary to cut the steel at joint section?
how to calculate quantity of cement,sand & aggregate for u.c.r / r.r masonry in cm 1:6
can any one explain bar bending schedule of bems and columns and slabs ??
how much of quantity of material required for execution of one cubic meter of random rubble masonry in 1:3 cement mortar
1) What is meant by C-soil in geotechnical Engineering? 2) What is Eve board? 3) What will happen when heat is applied to cement? 4) what do you understand by the lateral dimention ?