how do we calculate quantity of cement , sand and
aggregates in 1 m3 of M30 grade concrete ?
Answer Posted / k.nabadwip sharma
Calculation for Cement:-
100 cft of conc in loose 144 to 154 cft required,average of
144 and 154 is 149 cft say 150 cft.
M25 = 1:1:2=4
150cft/4=37.5cft
37.5cft/1.2=31.25bags [1 bags of cement is 1.2cft]
=31.25/2.83=11bags [1 cft = 0.0283cum x 100 cft=2.83cum]
per cum cement required=11bags
Calculation for Sand:-
11bags x 1.2 cft = 13.2 cft = 13.2 x 0.0283=0.374 cum
Per cum sand required = 0.374cum
Calculation for Aggregate:
=0.374 x 2 = 0.747 cum
per cum Aggregate required = 0.747 cum
| Is This Answer Correct ? | 1 Yes | 5 No |
Post New Answer View All Answers
how find the cut length of tringular ring and any formula find out the quantity of circular brick work
give me the rate analysis for Bituminous Macadam and SDBC
what is the meaning of degreasing of the euipment or line.
how many types of survey and what are levelling instrument?
What is meant by a context menu in a cad software?
16 questions out of 55 were from the book GUPTA N GUPTA OBJECTIVE of civil engineering. Total ques were 4 ques from hydraullics, 7 from BMC, 4 FROM SOM, 4 from soil mechanics, 6 from transportation, 5 from engineering drawing.
How much Tolerance factors like 1. brick work 2.plaster 3.painting 4.floor tiling 5.wall tiling 6.shuttering 7.concreting 8.steel
why we are useing plastic under the lean concrete?and whts the advantage?
What is specific gravity???
what is the max. and mim. height of vertical post in informatry sign board which is used in highway projects.
How Can I know the wastages(%) of each work added in estimating the quantity of construction materials?(Eg. Ceiling Work, Brick Work,etc....)
how to calculate MR 9(derivation)
What are the disadvantages while using stone dust as filler in pavements?
if in column reinforcement lower dia connect to higher dia then from wher we want to start higher dia steel
How to calculate dry of volume of concrete constant?How it comes 1.54 or 1.57