a)If column dimensions are 250*400mm , what will be
cutting length for 8mm stirrups and how to calculate it? b)
If beam dimensions are 200*400mm , beam coveris 25mm , slab
cover is 20mm , what will be the cutting length for
stirrups? c)Column dimensions are 250*400mm , reinf. is
12nos. bar of 16mm dia , stirrups provided are two legged,
what will be the length of each ring?
Regards
Answer Posted / shashank
IN CASE OF COLUMN-
DIM.-200X400mm
CONCRETE COVER-
FOR COLUMN THICKNESS <250mm=25mm
FOR COLUMN THICKNESS >250mm=40mm
LENGHT OF TIE- 2A+2B=2X200+2X400=1200mm
NOW DEDUCT CONCRETE COVER-LENGTH OF TIE-COCNRETE COVER=1200-
2X40=1120MM
ALSO, DEDCUT BENDS- 2D FOR 45degrees
D FOR 90degrees
THEREFORE- CUT LENGTH OF TIE-1120-DX5=1120-2X8=1104mm(NO.
OF BENDS -5 )
Length of Hooks=10d=10x8=80MM
NO. OF hooks=2
Therefore-Length of Hook=2x20=160MM
CUTTING LENGHT OF BAR=1104+160=1264MM=1.264m
| Is This Answer Correct ? | 30 Yes | 19 No |
Post New Answer View All Answers
What you understand by building codes?
what is the formula for Mass of cement grout (Dg)=???
The internal dimensions of a wire house 15m*5.6m and the maximum height of piles is 2.70m. What is the maximum number of bags to be stored in two piles ?
why demand factor less then 1 ?
Give list of building construction equipment & explain about them in brief. How much is output of JCB, POCLAIN, Steel cutting & bending machine, material hoist, tower crane?
In how many types u can do POP on ceiling and walls(on which material or by using which material)? b) what is the difference between dry , oil bound, enamel, acrlyic type of painting? 2nd :- I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?
What distance in meters on the ground is the equivalent of one second of arc in longitude or latitude?
I have an span length 16 ft c/c
what is the 0 value in quantity surveying
suppose we have a tendency to make a hole on the surface of the simple supported beam, than where we goes to make it?
how to calculate total cost for slab 35'×8'
how find the cut length of tringular ring and any formula find out the quantity of circular brick work
What are the applications of modulus of elasticity?
What is the cost difference between site mix and ready mix concrete per cubic meter
how to calculate the concrete mix m30 by volume