a)If column dimensions are 250*400mm , what will be
cutting length for 8mm stirrups and how to calculate it? b)
If beam dimensions are 200*400mm , beam coveris 25mm , slab
cover is 20mm , what will be the cutting length for
stirrups? c)Column dimensions are 250*400mm , reinf. is
12nos. bar of 16mm dia , stirrups provided are two legged,
what will be the length of each ring?
Regards
Answer Posted / shashank
IN CASE OF COLUMN-
DIM.-200X400mm
CONCRETE COVER-
FOR COLUMN THICKNESS <250mm=25mm
FOR COLUMN THICKNESS >250mm=40mm
LENGHT OF TIE- 2A+2B=2X200+2X400=1200mm
NOW DEDUCT CONCRETE COVER-LENGTH OF TIE-COCNRETE COVER=1200-
2X40=1120MM
ALSO, DEDCUT BENDS- 2D FOR 45degrees
D FOR 90degrees
THEREFORE- CUT LENGTH OF TIE-1120-DX5=1120-2X8=1104mm(NO.
OF BENDS -5 )
Length of Hooks=10d=10x8=80MM
NO. OF hooks=2
Therefore-Length of Hook=2x20=160MM
CUTTING LENGHT OF BAR=1104+160=1264MM=1.264m
Is This Answer Correct ? | 30 Yes | 19 No |
Post New Answer View All Answers
What is the difference between one-way slab and two-way slab?
Where is the worlds longest elevator and how long is it?
Difference between lime, distemper and plastic emulsion?
Design a reinforced concrete combined footing (rectangular) for two columns located 3.60 metres apart. The overall sizes of the columns are 40cm x 40cm and 69cm x 60cm and the loads on them are 1000 kn and 1500 kn respectively. The space available for the width of the footing is restricted to 180cm. The S.B.C. of the soil is 280 kn/mm2 use M15 concrete.
how statics is different from dynamics
while doing the structural works of a simple ground+1 villa, can the columns be continued immediately after neck columns without tie beam, while the tie beam to be done after columns concreting.
what is the clear cover for shearwall?
SAND AND STONE AGGREGATES WASTAGE PERCENTAGE IN CONCRETING WORK?
which method is used in semi-rigid connection design??
Is it possible to make a feature using an overdefined sketch?
how to calclate the SHUTTERING TAKEN CONCRETE LOAD? WHAT IS THE LOAD BEARING CAPACITY IN STEEL SHUTTERING PLATE? WHAT IS THE CONCRETE LOAD IN (MASS) IN THE SHUTTERING PLATE. PLATE SIZE IS 120CM* 90CM CONCRETE WALL LENGTH IS 10M ,WIDE IS 60CM, HEIGHT IS 1.2M PLS TO SENT THE CALCULATION.
What is the difference between built area and super built up area?
Consumption of Binding wire for fixing of cover block in vertical surface
what is a well
What is limit state method and working stress method and ultimate method