Answer Posted / vikadent
As a rule of thumb, the optimum loading is between 50% to 70
% and my reference is Electrical installation guide by
Schneider and this is the range where the losses are minimum
inside the transformer.
| Is This Answer Correct ? | 0 Yes | 3 No |
Post New Answer View All Answers
A double circuit with dog conductor 66KV Transmission line from wind farm evacuation to feeding substation having capacity of 25MW for transmission. Can same transmission network be considered for further expansion of Power & how much in MW. If we need to expand next 10-15 MW more will there any augmentation is required in transmission network? Kindly reply asap.
Classify milling machines.
redundant connection in contactor?
Is it advantages of having star-delta vfd than normal star vfd , if yes why?
What does the kvar means?
What are the advantages of thermal power plant?
ACB & VCB how do work and saftes and how can maintenance in this and parts name show with picture
what is control supply rating of a machine
3ph motor running with unequal kw and different pf what are the reasons
What is PQA???Applications........
L.A. (Lightening Arrester) is located at a place from where transmission line enters the transmitting substation. So L.A. (Lightening Arrester) is the first equipments which has to encounter with lightening, high voltage surges and switching surges. It has to absorb energy of lightening, high voltage surges, and switching surges. L.A. (Lightening Arrester) is made up of layers of semiconductors. If these layers can not tolerate energy released by lightening, high voltage surges, and switching surges the L.A. (Lightening Arrester) blasts.
How To increase Knowledge Of boliler regarding To Only Electrical Field..
What are IR values and what it should be for coil and for insulator
how we can do the insulation on secondary of ct explain and so that tan delta will within limit
State nyquist stability criterion.