How to take Vector group test of Transformer?
Answer Posted / raj_singh_0376
Procedure of vector group test of transformer
Let’s have a YNd11 transformer.
1) Connect neutral point of star connected winding with earth.
2) Join 1U of HV and 2W of LV together.
3) Apply 415V, three phase supply to HV terminals.
4) Measure voltages between terminals 2U – 1N, 2V – 1N, 2W – 1N, that means voltages between each LV terminal and HV neutral.
5) Also measure voltages between terminals 2V – 1V, 2W – 1W and 2V – 1W.
For YNd11 transformer, we will find,
2U – 1N > 2V – 1N > 2W – 1N
2V – 1W > 2V – 1V or 2W – 1W
| Is This Answer Correct ? | 1 Yes | 1 No |
Post New Answer View All Answers
Meter p.t. ratio= 3×230/400 , c.t.ratio = 3×1 (2) A what is m.f.
WHAT IS THE DIFFERENCE BETWEEN GENERAL INVERTER AND SOLOR INVERTER TELL ME PLZ
what happen if the load connected to the induction motor is taken away? the same question for synchoronous generator in synch i think that the the exitation voltage will appear on the terminal only if so plz answer me
What is the use of bundle conductors?
working principle of AC Servo Motor with its construction
what is difference between 2 pole structure and 4 pole structure in transformer yard
what is the safty of poly phase tranformer?
please send the last 5 years {{{JUNIOR ENGINEER - ELECTICAL, ELECTRONICS RRB CHENNAI and secundrabad}}} TECHNICAL question papers TO MY EMAIL ID dinesh100701@gmail.com
for hipot test on 33kV busbar, we will test on 70 kV or 56kV, what is the acceptable leackage current?
What is distance between electrical panel to land ?
is there any current and voltage drop on liquid resistance starter water/soda tank ?
1.how many earth pits are required for 1000 k.w plant include substion , transformer ? 2. how many earth pits are required for 500kva generator.what is formula to calcute?
are there rmu for 3 transformer?
What do you mean by reach and reach the point of the relay?
I have c license but I don't know eligibility of Max Kilo Volts under the electrical licensing board.