How many number of bricks required for 1 cum & how much mortar
quantity require for 1 cum
Answer Posted / m.k. dharmaraja
The brick size
1. 21x10x7.5= 380 to 400 Nos Mortar is 1.1 bags Cement(1:5)
2. 20x9x4.5 = 400 to 430 Nos Mortar is 1.25 bags Cement(1:5)
3. 19x8.5x7 = 450 to 480 Nos Mortar is 1.45 bags Cement(1:5)
This data is as per site details
Add the wastage in the quantity for 10percentage for all
above.
| Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
what is meant by csr in foundation? what is sbc?what is meant by contour line?
A 16 pile group, consisting of diameter concrete piles, were cast in situ in a clayey soil whose unconfined compressive strength is 1100 psf. Each pile is 60 ft long and the pile spacing is 2.5 times the pile diameter.The water table is at the ground surface and saturated unit weight of the clay is 118 lb/cu.ft. using a factor of safety 3 and a reduction factor =0.45, compute the allowable capacity of the piles acting as individuals
What is the quantity of metal 1 & metal 2 to be used in 100 cft concrete?
How to determine thee cut length for steel reinforcement bars in R.C.C design
Reinforced concrete: suppose you are doing rough estimate for purchase of rebar for reinforced concrete slab for single stores residential building. You know total concrete volume will be 100 m3. How many tons rebar 6, 10 and 12mm will you require for the project?
How to find CN by using arcgis 9.3?
How Can I know the wastages(%) of each work added in estimating the quantity of construction materials?(Eg. Ceiling Work, Brick Work,etc....)
though u r a civil engineer, y r u interested in tcs???
in the construction of residential building what type of tank are used?where?why & what is its purpose?
Design a shear wall of length 4.20 m and thickness of 250mm subjected to the following forces.Assume Fck = 25Mpa and Fy = 415Mpa and the wall is a high wall with central part 3440mm x 250mm and two 380mm x 760mm strong bands at each end with following loading. S.No. Loading Axial force Moment Shear 1 DL+LL 1950 600 20 2 Seismic load 250 4800 700
what is detail procedure of eccentric footing? plz. give solved exmple?
What are the different theories of failure under static load?
What is need for setting limits?
How to come 1.54 from dry to wet concrete?
What is the difference between routing maintenance and major maintenance in school facilities?