how to calculate 1:2:4 ratio concrete cement, sand, metal
and water please give me brief calculation
Answer Posted / decosta
For volume 1 cu.m
Consider:
Cement= 1x1/7=0.14 cu.m = 4 bags, since 1 bag= 0.035 litre
Sand= 1x2/7= 0.29 cu.m
aggregate= 1x4/7= 0.57 cu.m
When we sum up give us: 0.14 + 0.29 +0.59 = 1.02 cu.m
| Is This Answer Correct ? | 5 Yes | 9 No |
Post New Answer View All Answers
How to find out kg per Sft ?
what is parametre for M25 after 7 days strength
2. What are the advantages of your present job, things you like about it?
What are the skills required to become an architect?
Basic civil interview questionsÂ
in plate load test what is the thickness of plate 20mm 5mm 50mm none
what are the types of dimensioning?
how much brick, cement, and sand required in 1mtr X 0.23mtr X 1mtr brickwork(1:4), 230mm thick wall and 10mm thick mortar , brick size 230mm X 70mm X 110mm
Cut Linten (RCC-1:2:4)on 10" wall - what should be the width and hight of cut Linten? Secondly, 1 X 1.6 foot,4" thick window sun/rain shed (Chajja)should consume steel,Cement, sand and Stone chips?
What are the causes of building collapse?
How to build the floor to ceiling bookcase?
While calculating the weight of the steel per running meter, the formula used is [(dxd)/162]. Why 162 is used in denominator & how it is derived?
What do you meant by gui?
what is cross hair cursor?
What happens when water mixed with cowdung is used for priming instead of water for lifting water in pumps?