how much cement consumption in 1 sqmt of wall cleading work
(dedo)?
Answer Posted / sanchit guleria
thickness of neat cement layer is 1.5mm.
so cement required for 1sq.m= 1*0.0015=.0015cu.m
dry vol. of cement increased by 25% so (.0015+.0015/4)=.001875cum=.054 bag=2.67kg of cement
Is This Answer Correct ? | 2 Yes | 1 No |
Post New Answer View All Answers
What out turn civil works
115mm thickness brick work how to required mortar
What is an ice dam sock?
What is the difference between Hinged and pinned in Column ends
what is the Purpose of Adding 20% of wet mortar & 1/3rd to Dry Mortar for PCC & Plastering & Rcc .is there any standard method for adding this .?
sir iam dng my engg final yr (civil) iam intrested to write group_1 .if we write this exam what kind of jobs we get and what should be the minimum score for us to get qualified and iam having reservation too.
How to calculate(Thumb rule) the consumption of steel per cubic meter for different concrete members.
what is the 0 value in quantity surveying
what is column foundation
Explain what are the problems one might face while having a Cantilever balcony?
in levelling operation the first site on any change point is back site the second site on any change point is fore site the line commenses with fore sight & closes with backsight the line comensses with back sight & closes with fore sigh
what does the track parameter mean in staad.pro?
100mm block work 64 bags of cement used 150mm block work 286 bags of cement used 200mm block work 20 bags of cement used patly work (M15) 293 bags of cement used mortar ratio is 1:5 how to calculate volume of sand in cum & no. of bags
types of laps in column
Consumption of Binding wire for fixing of cover block in vertical surface