for M20 grade of concrete
Ratio 1:1.5:3
(i.e) cement : coarse aggregate : Fine Aggregate.
( jally ) ( sand )
1cubic metre cement = 1440KG
In the concrete 0.45% of the sand ratio is utilised for
cement.so for M20
= 0.45/3 X 1440
=0.15 X 1440
= 216Kg/cubicmetre
= 4.32Bags of cement/cubicmetre of concrete
| Is This Answer Correct ? | 4 Yes | 31 No |
Post New Answer View All Answers
what is the water cement ratio for plastering
During reclamation how can the occurrence of mud waves can be rectified?
give me the rate analysis for Bituminous Macadam and SDBC
How do you convert wind speed into force?
Use of coping on terrace wall and in 4" wall is compulsory or not ?
Please tell me Detail cost of providing& laying nominal mix design 1:2.5:5,40mm nominal size.curing complete e/c cost of form work in foundation and plinth i/c carriage.
What are the advantages of building a dam on the river nile?
What sizes of stones chips are used for foundation, column and floor casting. Please answer in detail.
which are the Indian auther books for STONE COLUMN/GRANULAR PILES?
How much material will consume for following specification water tank (9*7.5*6 feet)?
How can we make a hole in a solid rectangle using solidsworks?
could u tell me how to used deform stell bar in reinforce concret?i wanna know the general using in the site!
Describe the role of independent Quantity surveyor?
which red: used in roof teping, then use only cement
why is the column design?