1:2:4
cement = 6.35 bag per one cubic meter
= 6.35 x 50
= 317.5 kg
sand = 0.43 cubic meter (or)0.01218 cubic feet
aggregate = 0.86 cubic meter (or)0.02436 cubic feet
| Is This Answer Correct ? | 16 Yes | 6 No |
Post New Answer View All Answers
what is the use if we fixed butterfly ties in column and masonry work joint?....where we have to fix(distance)..
Which is the latest version of solidsworks?
is it fair to recruit another prestressing agency once earlier agency has provided guide cone for post stressing the Concrete -I girders? It is observed that the bearing plate of another agency is not matching with the earlier one resulting in protruded strands after stressing from the face of girder. Kindly advice.
What is the quantity of cement in mix m20 concrete?
how many mason and labaur work for a 1 brass bricks plz let me know the calculate & how to made calculation for this and whats the formulas for this?
how many sqft or cft of work done by a mason per day in all works such as brick,block,concrete,shuttering carpenter,reinforcement fabricator,painter,door window carpenter.....everything thank you
how we check the thickness and line of ceiling plaster.
What are the methods of measurement? Describe it shortly
How do you calculate the power of a centrifugal pump?
What is the per cu. mt. price of ready mix in Gujarat region.?
What is the compressive strength of fly ash bricks?
What is componsation
Specific gravity of cement?
manhole chamber having height of 2300 mm and thickness of brickwork is 230 mm and dia of opening covering is 560 mm and bottom length vertical is 1500 mm (1:4) brick masonry and plaster 12 mm on both sides..how to estimate the no bricks used with mortar cement bags and sand for total chamber including plaster.
How much for the BRC lapping in full yield and half yield < and which table to get it ?