Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

How to calculate the cement, sand quantity for plastering?
(10'x10')10mm thick ratio 1:5. wht"s the formula?

Answer Posted / naga

10'=3.04m
mix=1:5,
1/6=.1666+25%+30%=.71cu.m of cement

sand requires=3.5cu.m
plastering area=3.04x3.04x0.01=0.092416cu.m

Is This Answer Correct ?    17 Yes 9 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Why do we not deduct steel volume to find actual volume of concrete in practical as we have studied that,,, actual volume of concrete = volume of column- volume of steel pls explain with reference of IS code?????

2050


Design a rectangular channel.

2896


how much brick, cement, and sand required in 1mtr X 0.23mtr X 1mtr brickwork(1:4), 230mm thick wall and 10mm thick mortar , brick size 230mm X 70mm X 110mm

2029


sir how can we find the cement and sand required for making 4" drop

2142


How to take labor charges for construction of 1cum of concrete?

1149


What is construction mitigation management?

2306


what is differences between ferrock and concrete ?

2036


Write short note on construction programme for pile foundation.

5404


What is the coeffiencent Friction Angle between Steel and Ashphalt?

2995


What is the Null Point of chimney in Power Plant

3724


what"s the sort of beams?

2303


what is the function of GSB all class ?

1210


What is meant by cad?

1024


For removal of formwork of simply supported slab / beam from where to start the deshuttering? ( Max Bending moment of the simply supported beam is in the center hence is it required to start from the supports?)

2033


I want to know about rolling margin of steel :- For eg. If 2nos. bundle of 8mm dia steel with17 rods each of length 12m comes to store. During testing of 1m rod of each bundle it was found that 1rod has weight .405kg/m while other has .385kg/m. Now what will happen in case of steel payment and measurement payment ? Regards,

2478