How much binding wire is required for one tone reinforcement ?

Answer Posted / harathi nitin

As per Joglaker (Quantity Surveyor Book) it is mentioned as
for every quintal of steel reinforcement ( 1 quintal =
100kg) 0.9 to 1.3kg of binding wire is required

for 100kg of steel reinforcement = 0.9 to 1.3kg of binding
wire

for 1 tonne (1000kg) = 9 to 13kg binding wire will be
required

Is This Answer Correct ?    168 Yes 19 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Does degree of bend of rebars has any effect on strength of the member? For example- if a beam is designed with 45 degree bent up bar with respect to architechtural needs and is not 45 in practical so will there be any reduction in the strength of member?

1438


do you think we shall remove un wanted soil for foundation excavation even if the thickness of the soil strata is more than 8m ?

1185


what s the standrd size of pvc fittings ,like elbow, bend,tee etc ? please explain with figure ?

2001


Define different types of roof systems?

698


How much percentage of brick bats allowed in CD-75 bricks

1855






What is the amount of work done by a carpenter, bar Bender and plaster Mason in interior and exterior plaster

1805


use ofr concrete as per grade ?

1616


How to plan a project

1682


what is diversion?

1716


significance of specific surface area of particles?

1612


sir I got selected in rail vikas nigam limited and they call for interview but i don't what they will ask in interview please guide me if you have any experience

1891


Define What is Civil Engineering?

625


16 questions out of 55 were from the book GUPTA N GUPTA OBJECTIVE of civil engineering. Total ques were 4 ques from hydraullics, 7 from BMC, 4 FROM SOM, 4 from soil mechanics, 6 from transportation, 5 from engineering drawing.

17723


what post do you prefer to work in this company and why do you think you can serve better in such position?

2209


Why Vitrified tile are getting pop up.

502