Method of findingthe dry ingredient quantity of 1 m3
concrete.
Answer Posted / jj r
For M-15- 1:2:4 you just add the all ratio
1+2+4=7 then for 1 m3(cement=1/7,F.A=2/7,C.A=4/7) in CUM...
tats all
| Is This Answer Correct ? | 4 Yes | 3 No |
Post New Answer View All Answers
How cracks in concrete can be avoided?
What is the difference between chamfer and fillet?
How to calculate or what is the process of calculation for making 1Metre squre area by AAC Blok which quantity of Cement, Sand & Chips are to be required?
Define absolute co-ordinates?
Which is the latest version of solidsworks?
find the discharge of water through a horizental venturimeter having 400mm dia at the inlet main and 150mm dia at thorat.if the diffrential gauge between inlet and thorat shows a pressure head of 25cm mercury. assume coefficient discharge 0.98 and specfic gravity of mercury as 13.6.
what are the challenges of being a team leader and a supervisor?
how many tonnes equals to one cubic feet?
why we create short columns under grade slab?
In foundation design, while we do the base pressure check, we normally check if the attained pressure value is less than the GROSS BEARING CAPACITY of the soil which is the sum of net bearing capacity of soil and the overburden pressure. Actually, the overburden pressure acts against the net bearing capacity of the soil and I feel that we are actually increasing the bearing capacity value and doing the check. I feel that this is NOT right. Please clarify on this.
Define graphics window?
a solid steel rod length 2m dia and 20mm vertically hangs from celling and has a collar firmly atteched to it. above the collar an annular rubber washer of 40mm th. having stifness k = 5n/mm is placed. determine maximum stress in the rod caused by mass of 5 kg falling through a height of 1.2m.
what do you know that m20,m25
How to calculate dry of volume of concrete constant?How it comes 1.54 or 1.57
importance of the soundness test to determine the quality of cement use for any construction