how many 1st class bricks in 1cu feet?
Answer Posted / er a.v.s.v.prasad raju
1 Cft = 30 cm x 30 cm x 30 cm = 27,000 cubic cm
Standard size of brick = 9" x 4" x 3" (or) 22.5 cm x 10 cm
x 7.5" = 1687.50 cubic cm.
Number of bricks required in a cft = 27,000/1687.5 = 16 no's
Note: Cement mortor is not considered.
Er A.V.S.V.Prasad Raju
| Is This Answer Correct ? | 5 Yes | 7 No |
Post New Answer View All Answers
asubmerged weir is one in which the water level on the down stream side of the weir is just at the crest level below the crest level above the crest level at stamp elevation as water surface on upstream
Where will be the maximum bending moment in a TEE Beam?
Explain what is Critical Path Method (C.P.M)?
how to calculate spacing rod in column
How did the romans get water up hills using aqua ducts?
What are the responsibilities of a site manager?
I need old MMUP exam question and answer for Civil engineering
HOE TO YOU PLAN TO ACCHIEVE THE GOALS?
What is made from large rocks, which protects the base of cliffs?
How much cement is require in one sqft area in a G+3 residential construction.
how to determine the correctness of proportion used in cement mortor and various IS codes to determine the same?
I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?
Formula of mid span bar
What is difference between code and standard and specification?
I am doing a engineering contract with GOI. I have purchased certain material from outside Maharashtra and paid CST on that material @ 5.25%. Please intimate whether I will be liable for VAT or VAT on works contract or not.