extremely urgent please, why a fuse is used before
voltmeter but not with a ammeter connected to a CT(current
transformer),thanks in anticipation.
Answer Posted / syed shoeb ullah hussaini
look man ... In c.t load is
connected to the primary
winding and ammeter is
connected to secondary
winding hence there no fuse
in c.t .... Similary there no fuse
in potential transformer as
the voltmeter is connected on
secondary side with closed
loop of secondary and
winding .... P.t is step down
transformer hence in this also
no fuse is used .... Its was a
trick question to measure
your knowledge
| Is This Answer Correct ? | 5 Yes | 2 No |
Post New Answer View All Answers
l&t switch FN 63 handle position can we change
How can we findout the maximum efficiancy of Transformer? At which load?
what is feed back and what are feed back amplifiers?
bsec exam syllabus (mis)
What is non-minimum phase transfer function?
how to find 5 kilo meter long under ground 33 kv cable fault location if IR VALUE shows 0.05 M ohm @5000 volt.and cable fault locator shows some time fault distance 3 kilo meter ,3.7 kilo meter and some time 1 kilo meter? now how to find the fault location that where is leakage. note--it is tested with 5000 kv megger and insulation resistance is 0.05 M ohm. and some time 0.03 M ohm comes.
why we can use 1 to 5V dc
What is a dc motor?
Please help me regarding my one concern. - During earth pit testing we noticed that the Clean earth pit and dirty earth pit showing continuity (Resistance value - 5ohm) . I want to know that if both earth pit have separate location and there is not internal looping between PIT then why such continuity is showing on it . Because of this issue the field side all earthing point showing short. In PLC panel we are providing two types of earthing cable which is coming from separate earth pit (Clean and Dirty earth pit) because of earth PIT showing short our PLC is not complying spec . please help regarding this issues.
How the setting of the vector surge relay shall be calculated when the relay is to be used for Grid islanding application?
If two Transformers are connected in parallel having impedance of 50KA in both transformers will the impedance increase or decrease after connecting transformers in parallel?
what is the difference between online & offline caliberation of KWH meters. Can Digital meters be caliberated
What is the requirement of grounding the neutral of single phase generators on load? If the neutral is not grounded, what will be the effect?
what is the ckt diagram of a tubelight and is it the simplest ckt of electrical engineering and also the component?
why and how voltage sharing in transformer, during magnetic balance test ?