Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

How much Strength of the cube can attain in 7days
comparative 28 days strength?(as per IS code) ( specify the
ref.clause also)

Answer Posted / kumaresan

at Seven days, it should be 70% and at 28 days it should be
100%

Is This Answer Correct ?    13 Yes 1 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

A doubly reinforced concrete beam is 25 cm wide and 50cm deep to the centre of tension reinforcement. The centre of compression is steel is 5cm from the compression edge. The areas of the compression and the tension steel are 10.16cm2 and 12.56 cm2 if m=18 and the bending moment at the section is 7,000,000 N-cm. Calculate the stress in concrete and steel.

2174


What is the FE 250 structural steel of 8mm tk plate testing sample intervals with IS code or international code?

2316


Dear Sir I Mahesh C. Bhamre have already given a Exam for Superintendent Officer / Public relation Officer Exam Dharmday Aaukta held at Nashik on Date 29/08/2010. My seat no was 5040247. and my cell no is 9822677994. and my mail Id is - mahesh.bhamre@rediffmail.com So can you pl send me details of result of respective exams. Thanking you in Anticipation.

2267


why does the most of civil engg is not intersted to going for teaching field?

2076


How to avoid fly ash seed ball formations in the concrete mixer while mixing of raw materials for fly ash block manufacturing?

1907


if a pipe those configuration (ASTM c 76 class b 450mm dia 2500mm length) fixing for water course those lining of water is 7000 running meter. my question is that if 8 joints of pipe ls leakage and we have not permission to stop the water so which treatment we apply on joint in that in condition.

2144


pls give me some basic informations in construction of a structure?

2057


What is difference between engineering stress and true stress?

1187


Reinforcement details at hinged joint

3152


what is the use in canals of longitudinal drains and cross drains in lining areas?

1945


what is castigliano theaorem

2273


what is conventional shuttering rate per square feet of built up area? what is Mivan shuttering rate per square feet of built up area? what is coupler shuttering rate per square feet of built up area?

5101


Minimum concrete cover in slabs, columns, beams, foundation and other st?

1280


how to preaper for interview wat they asked in interview give me idea

2701


What out turn civil works

6820