Please tell me the difference between nominal and clear
cover. Thanks.
Answer Posted / mustafa mohd layeak
In beam of b*D dimension. considering bottom section of beam
effective cover is the distance between centre of main
bottom longitudinal rebar to the concrete extreme fibre
(bottom edge of beam).
clear cover is distance between concrete extreme fibre and
bottom edge of a stirrup
Similarly at the top section of beam
Is This Answer Correct ? | 45 Yes | 8 No |
Post New Answer View All Answers
Define current ucs?
brickwork labour rate per cum ?
What is the bowing depth after stressing of PSC Girder of various spans and various dia of strands?
Hi all, please guide me about the volume. And percentage. Of steel fibre to be used. My project. Is Sifcon.
How to find out slope footing concrete
Formula for calculation volume of essentric footing
What is meant by Crystal Concrete?
what is the clear cover for shearwall?
How to identify the vitrified tile and ceramic tile by observation only after executing the job.
How many are the types of joints?
1. For 10sq.m area(47 kg bitumen contain) of 45 mm thick bitumen mix layer..how much bitumen is required for 1600 sq.m and how much aggregate need for that ?? 2. And much tonnage of bitumen mix required for 10 sq.m area of 45 mm thick. Please give answer...
What is the meaning of soil reinforcement?
. Write a C program to perform following functions:- a. Declare one integer variable of all the storage classes. b. Print all the variables without assigning any values in tabular format. a. The tabular format must contain the variable name, type, storage class and printed value on the screen in RED color.
How many square meter can a worker/labor demolish a structure per day?
WHAT GOAL DO YOU HAVE IN YOUR CARRIER?