Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

how the lap length is calculated in reinforcement of 110mm
dia steel of Length 15.00 mtrs. & grade of concrete is M20

Answer Posted / mithosh g nair

if dia is 110 mm then that bar must be welded. bars below 32mm dia
the lap length

In tension 50* dia
In compression 45 * dia

Is This Answer Correct ?    34 Yes 4 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?

2080


What is Density of cement, sand & aggregate ?

1491


where i can get material costs on weekly basis

2144


Calculate the maximum allowable speed on a horizontal curve of radius 350m if the maximum allowable values of the lateral coefficient of friction are 0.14 and the rate of superelevation is 0.08.

2501


CAN V USE CRUSH SAND FOR CLAY BRICK MASONARY

1131


Suppose a new brick wall is being constructed,and the courses and not aligned horizontally,what negetives can it cause?

1964


yasser arfatcompleted his degree in civil from which university

2248


What is hybrid foundation?

1103


1m square 20mm plastering how much of water need curing work

1884


Before casting a basement roof slab which is connected with retaining wall surcharge load (i.e. sand or earth filling) outside the retaining wall is prohibited because of––

2391


the volume of cement req for 70cum of brickwork in 1:6 cement mortar is approx is equal to 3cum 5cum 7cum 1ocum

2021


How much form and scaffolding per cubic meter volume of concrete class ''A'', ''B'', and ''C''

2154


"Gates of the dams are generally designed of curved shape". Why?

2053


In reclamation works what are the importance of geotextiles and sand?

1129


What is the cost difference between site mix and ready mix concrete per cubic meter

1864