What is diffrenece between Installation and Commissing ????
Answer Posted / mecheng
Installation is the process of placing, positioning, building and connecting equipment in its proposed and design nominated location in accordance with design specifications.
Commissioning is the start up of the equipment for the first time. It is when you run the equipment and carry out tests to verify it is running as intended i.e. to design specifications. Commissioning tests are normally run against a design data baseline. Commissioning also includes things like checking oil levels, fluid levels, temperatures, pressures and for general issues that are contradictory to the intended correct operation of the equipment.
| Is This Answer Correct ? | 16 Yes | 2 No |
Post New Answer View All Answers
What will be expected the cut-off of J.E Mechanical exam of RRB on 19/12/2010 ?
Anybody please send me the papers of the reliance exam (apti and tech) so that i can go through it) mail me at raminder_verma@rediffmail.com
Which reactor requires no moderator ?
What do you do when in your duty, ME alarm oil mist detect high density?
What causes hardness in steel ? How heat treatment alters properties of steel ?
Name the machines you know?
What causes turbocharger surging?
What is the weight of 1m3 of seawater?
What is the melting temperature of the cng long tube fusible plug? And can I use lead solder Sn97Cu3 (Melting temp S/L 227-309 °C) Materials of tube : AISI 4130 Alloy steel
draw p-v dia distingshing naturally aspirated and supercharged engine with reference to pumping loss?
What is the purpose of stern tube?
i am appearing for the interview of the company SANDVIK??so if u can send me some questions or suggestions on how to prepare,it would be of great help to me.u can send the above at ekjain@yahoo.co.in.thanking you.
what is the procedure to start the turbine?
Where mixed flow type compressors are used?
how water evaporated in sea