In two way slab where should we stop the work at end of the day?
Answer Posted / ajay kulkarni
it should be a little ahead towerds center form point of
contraflexure to allow for bonding roughfly @ L/3 from
either ends for two way slab.
| Is This Answer Correct ? | 11 Yes | 0 No |
Post New Answer View All Answers
what"s the sort of beams?
do we consider shrinkage factor for calculating cement consumption for CM mixes for different works?
is there any thumb rule for calculating construction cost of the building with pile foundation per sft. area?
What do you meant by gui?
how to compute slab reinforcements on step by step procedures??
HOw much % of premium on DSR-2013 currently
How much material is required for constructing a 2 Lane 2Km rigid pavement road
HOW MUCH STEEL REQUIRED FOR SLAB OF AREA 23'3"*18.3"? FOR SLAB HOW MUCH DIAMETER BAR WILL USE?
How much sand and cement requirement for 1 SQM 125mm thickness Brickwork
Under what circumstances should pot bearings be used instead of elastomeric bearings?
What is diversion tunnel in a dam?
Define What glue is least sticky?
What is the unit standard weight,thicknessof C.I>Pipe of various Dia upto200 MM(as per IS1538)
when it is noted "JAMB SIM" what is the term "SIM" and what does it mean?
all technical question