Answer Posted / tukuna das
M30 means , proportion 1:1:2 , so that
Total Volume = 1m3
we take 52% extra for dry volume , miss handling etc then ,
total volume = 1* 1.52 = 1.52 m3
Quantity of cement required = 1.52/(1+1+2)=0.38/0.035= 10.857bags = 11 bags
Quantity of sand required = 0.38*1=0.38m3
Quantity of aggregate required = 0.38*2 = 0.76m3
Is This Answer Correct ? | 12 Yes | 12 No |
Post New Answer View All Answers
What is the difference between routing maintenance and major maintenance in school facilities?
What is aggregate?
is there any codal provision for soil cousion over the Hume pipe of Dia 1.2 m.
What is made from large rocks, which protects the base of cliffs?
Different sizes of Hollow blocks and its weight. Thanks.
How to calculate material and labor required for 100 m2 plaster?
how water proof chemicals act in concrete to avoid leek?
Differentiate first angle & third angle projection?
Civil engineering related
for 32 dia (EQR HYSD steel) bar how much deduction for 45 and 90 degree band
what is the cost difference of a same structure when it is constructed with brick masonary and when it is constructed with block masonary and concrete as a frame structure????????????????????????
what is mc arther pile?
In a concrete grade C35A, C & A stands for what and equalent cube strength?
How u can calculate the Octagon ring distance from center of raft in 275 mtr chimney slipform errection? cantact no:0993455097
writte a c prog. to acept 5 no. from consule and then display them back on consulte in ascending order