we have LPG spherical Tank and we want to install DP Xmtr
for level measurement.below are the physical measurements
Total height of tank is 1850 mtr but 0% level is 1000mm
above bottom and 100% level is 450 below upper side.What is
the LRV and URV and please mention the formula .The SG of
LPG is 0.53 and Wet Leg method will be used.
Answer Posted / nestor
let us consider at 100% 450meters upper side so the wet leg measures:
1850 - (450 meter + 1 meter) = 1399 meter
so height(specific gravity) = 1399 (0.53) = 741.47 meter
span = URV-LRV
LRV = 1 meter(0.53) = 0.53 meter
so URV = span+LRV = 741.47 + 0.53 = 742 meter
| Is This Answer Correct ? | 0 Yes | 3 No |
Post New Answer View All Answers
Why not come out analog output in ABB EL3020 when display show correct value
How u measure the massflow in orifice flow measurement techniques
can any one explain in which term we are flow flow is it volumetric r is it mass? and y
I am having a Phoenix digital to modbus converter. The o/p of the same is connected to flow computer FB407. But the digital signals are updated only after one minute in the flow computer. what may be the cause of delay in communication? Flow computer is having a scanning period of less than 1 sec.
Which type of diaphragm use in costic line, dm water line, natural gas line, oil line?
What is the difference between uv and ir scanners? and what is the workig principle of both
i want to find out iffco get test paper
Sir,I am going to sit for IOCL written test exam. recently.Can anyone tell me the name of 'Objective type Question Book on Instrumentation Engineering ' which will help me. Pl. mail to bidyut_71@rediffmail.com / bidyut.saha2008@indiatimes.com / bidyut.saha09@yahoo.in
Why upper weighing limit of electronics balance is 90% of the total weighing capacity?
how to calculate signal cable sizing? and multipair cable sizing??explain in brief?
what is the field bus calble ? what are diffrences in orang colur cable and black coular calble ?
I m appointed as an automation trainee engineer in small firm in that I am only the one , my company give me a project on s7-200 as i m beginner I don't know how to program so please send me the helpful site so that I complete my project before deadline....please help me out in this critical situation.
who's take first position in process in the timing of new installation flow transmitter and control vavle. give the answer with logical trick.
the whole paper was based on Transducers..questions like define repeatability, error,accuracy,precision..den there were many q. on the conversion of Pa to mmHg and other units.. also..der wer few Q. on some level sensors(with diagram)
Which types of quections asked in interview for FORMULATION PLANT (PHARMA)