Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

how can we can take BDV test in transformer?

Answer Posted / ramachandra reddy

On TRANSFORMER OIL BREAK DOWN VOLTAGE test is carried out which is done on field while filling the oil in transformer. This process is also called oil filtration.
1.Take sample from top of Transformer before filtration.
2.The BDV of oil should withstood min 50 KV
3.The gap between the test electrodes sample to be 2.5mm maintained
4.At least 5 sample(top/bottom) should be checked separately while filtration.
5. The samples should withstand 50 kv for 1 min.
5. Take the average of all the samples timings.You will get value.
7.Procedure
a.Voltage should be gradually increased from 0.
b. At one point Flash will take place and that point is
termed as Bread down Voltage

Is This Answer Correct ?    26 Yes 4 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

While HT line put on to activate ACB in low tention panel VCB tripping instantly.why it happens

2045


what is the diference between the 4pole & 6pole DC Motors & what is advantage 6pole over the 4pole ?

1851


DESCRIBE THE CONSTRUCTION ANDOPERATION OF BELT CONVEYORS AND SCR CONVEYORS , DRAW NEAT SKETCHES

2020


what is auto re-closer?

2525


When we need up only in o/p 440v, so why we use directly in 11kva in input?

1637


How can we find out LT UG cable fault (size,from-4*25mm sqr to 4*300mm sqr)? How mani types UG cable faults?

3001


along with technical test papers

1561


advantage and disadvantage of team work?

1647


can we synchronize star system generators with delta system transmission line ? and how ?

2775


How to calculate flow of water delivered by pump when pressure & size of pipe line is given

2245


Is the installation of the filter cloths necessary before spreading the gravels at the transformer yards?

1894


what is motor capacity of 80TR chiller? and also say what is the formula related temperature, motor capacity, TR?

2226


how ups works ? various parts of ups and working principle

1904


Lt motor sfu flashing reasons?

1738


What is negative sequence over voltage element?

1897