Answer Posted / ramachandra reddy
On TRANSFORMER OIL BREAK DOWN VOLTAGE test is carried out which is done on field while filling the oil in transformer. This process is also called oil filtration.
1.Take sample from top of Transformer before filtration.
2.The BDV of oil should withstood min 50 KV
3.The gap between the test electrodes sample to be 2.5mm maintained
4.At least 5 sample(top/bottom) should be checked separately while filtration.
5. The samples should withstand 50 kv for 1 min.
5. Take the average of all the samples timings.You will get value.
7.Procedure
a.Voltage should be gradually increased from 0.
b. At one point Flash will take place and that point is
termed as Bread down Voltage
| Is This Answer Correct ? | 26 Yes | 4 No |
Post New Answer View All Answers
While HT line put on to activate ACB in low tention panel VCB tripping instantly.why it happens
what is the diference between the 4pole & 6pole DC Motors & what is advantage 6pole over the 4pole ?
DESCRIBE THE CONSTRUCTION ANDOPERATION OF BELT CONVEYORS AND SCR CONVEYORS , DRAW NEAT SKETCHES
what is auto re-closer?
When we need up only in o/p 440v, so why we use directly in 11kva in input?
How can we find out LT UG cable fault (size,from-4*25mm sqr to 4*300mm sqr)? How mani types UG cable faults?
along with technical test papers
advantage and disadvantage of team work?
can we synchronize star system generators with delta system transmission line ? and how ?
How to calculate flow of water delivered by pump when pressure & size of pipe line is given
Is the installation of the filter cloths necessary before spreading the gravels at the transformer yards?
what is motor capacity of 80TR chiller? and also say what is the formula related temperature, motor capacity, TR?
how ups works ? various parts of ups and working principle
Lt motor sfu flashing reasons?
What is negative sequence over voltage element?