How much Strength of the cube can attain in 7days
comparative 28 days strength?(as per IS code) ( specify the
ref.clause also)
Answer Posted / shri
at 7 days 2/3 of grade and at 14 days 1/3 of grade
Is This Answer Correct ? | 7 Yes | 3 No |
Post New Answer View All Answers
i have boiler of 35 tone and wanted dig out foundation is there any body to help me to carry out calculation for the foundation like
why demand factor less then 1 ?
contractor receive 100 MT steel.after compliting the work the contractor refund 90 MT steel.How reconsilation of steel done?
What are the problems one might face while having a Cantilever balcony?
strength of bitumen concrete with 80-100 & 60-70 grade bitumen
Why should appointment store person for project ? what is the benefits for company ?
HOW TO CLACULATE CEMENT AND SAND CONSUMPTION FOR THE STAIRCASE KOTA FLOORING IN THE RATIO OF 1:4 50 MM THICKNESS
which software is better for design and analysis of buildings (stadd pro ) or (Etabs)
What is the origin of name railway sleepers?
How many days should curing of plastering, brick work and concrete
Can a wave happen in the middle of the ocean like in the movie poseidon 2006?
How much cement,sand,bricks and water needed for 1square metre brick work?
how do i remedy a foundatiom that the column bases was cast and aftet 28days crushing the conprehensive strength of the concrete fall below the specification 25N/mm2
in 2 way slab can additional compressive reinforcement can be provided if yes than in which conditions it is required ?
1.what is the mix proportion for cement soil compressed earth blocks? 2.how to calculate the mix proportion for cement stablised earth soil blocks?