We have 3 Gensets 1.500kva,2.380kva,3.250kva How can we
connect in common busbar&we have variable load.
Answer Posted / milinda4p
to connect 2 or more generators to a common bus those
generators should be synchronised.it means
1. frequency should be same (every generator should operate
in same frequency)
2.voltage magnitudes should be same at each bus (i:e if the
generators have different rated voltage outputs correct
transformers should be used to get the same voltages at the bus)
but the POWER RATING is not going to cause any problem for
synchronizing
But in supplying a load after connecting it is important to
adjust the power supplied according to the load.( should
maintain the frequency of the system in constant value. if
not the rotor speeds of the generators should go up or down
causing and destruction or stopping of generators )
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
What is the difference between isolators and electrical circuit breakers?
what ispositive, negative, zero sequence impedence?
when qty of cable being purchased is not sufficient according to the standard,what should the inspector do to ensure its quality according to the standard?
What are the reasons for the parallel operation of transformers?
What is the most important precaution in any experiment with d.c. Shunt motor?
how to calculate transformer turn primary & secondary side 11kv to 420v
In a synchronous motor. if start is running at high speed. What will be the starting torque : Higher Lower Zero
1. Design a counter which counts 0, 4, 8, 2, 6, and repeats using: 1.a using JK flip flops 1.b using T flip flops 1.c using D flip flops
what is the method of earthing of a transformer using electrodes?
what are the applications of TIG welding
what is a power factor?
what are the steps involved in generator load test?
WHAT SHOULD BE THE BEST CURRENT RATINGS (PRIMARY / SECONDARY)FOR A CT INSTALLED AT THE INCOMING 11KV PANE? WILL IT BE CALCULATED ON THE BASES OF MAXIMUM DEMANT VALUE OR ON SUM OF ALL TRANSFORMER'S KVA? NOMALLY MAX DEMAND REPRESENT THE MAXIMUM OPERATING LOAD OF THE PLANT AND TOTAL KVA OF (SAY 5 NUMBERS TRANSFORMERS) REPRESENT THE CONNECTED LOAD. WHICH i.e. MAX DEMAND KVA OR CONNECTED KVA ARE BETTER TO USE FOR CT CURRENT CALCULATION? PLEASE ANSWER.
i am electrical and elctronics engg passed out in 2009 want to attend for reliance placements.plz send me apttitude ,technical and hr question answers to my mail plz. my mail id-kat.bindas@gmail.com
Percentage losses in power generation?