1sqm tile laying how much cement required?

Answer Posted / dinesh

If CM 1:4 and 20mm tk

cement= 1/4*1440= 360 kg/cum

for 20mm tk = 360* 0.02 = 7.2 kg/ sqm

Is This Answer Correct ?    51 Yes 19 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

in staad ,why we realease a moment of a member ? what is affect if we realease a moment

1725


how to shuttering is used in slab

1313


How to calculate unit weight of concrete for m40 grade.

3423


can any one tell me in detail footing estimation .. i am new here in dubai so facing lots of problem...

1661


Sir, Iam Applied in rrb for the posts of Junior Engineer.I want to know about the or question previews to study well.Pl send it to shukla_varun1985@yahoo.com.

1713






Can anybody help by describing each and every step in short, used while giving a building layout by total station? Regards

1576


How cracks in concrete can be avoided?

637


may i know the detailed description of cutting length

1631


how will calculate 4"thick solid block quantities 1m3 sand cement ratio and breack up detail

3486


manhole height is 1500 mm and width of brickwork is 230 mm dia of manhole covering is 560 mm brick masonry 1:4 horizontal length is 1500 mm and plaster 12 mm thick on both side 1:3. how to estimate the quantity of brickwork with mortar cement and sand for manhole chamber.

1646


please send latest placement papers of hpcl officers trainee test. i will be very thankful to you.

1814


please what are the required bars for a beams of 6mx6m and 450x300mm, one is continuous and the the second is discontinuous ..Its a commercial building (church)

1344


What Are The Different Type Of Slump Test Indications?

811


What is the difference between chamfer and fillet?

788


How do you calculate the power of centrifugal pump?

645