What are the Design Mix proportion,and where they are used
Answer Posted / arjun
Design Mix Proportion includes cement, sand, aggregate,
water and admixtures for getting high compressive strength
of concrete with suitable proportions. generally in
different locations the properties of these materials is
different so aviod the genaralproportion like 1:2:4 or
1:1.5:3 various samples are taken randomly upto getting
good results mix design can be done.
design mix normally used in all works like Mass Concreting,
Concrete PAvements & Bridges, Dams, Flyovers and huge
structures
| Is This Answer Correct ? | 4 Yes | 0 No |
Post New Answer View All Answers
can any one give me sample question paper of BHEL at mdansari86@gmail.com as i m appearing for the same exam.
plz.show development and anchorage length in simple diagram.
can u plz send me ntpc placement papers(civil engineering) at mohit_verma21@yahoo.com
Technical Question of Civil Engineering
water leak detection system question & answer
can you mail me detailed procedure,entire syllabus and practice papers of mpsc civil engineering branch.I am in third year now
400 ku d/c clearess ketan hota hai?
While calculating the weight of the steel per running meter, the formula used is [(dxd)/162]. Why 162 is used in denominator & how it is derived?
Re: Can anybody help me by attaching files , formats for quality checks of common building materials like cement , concrete , bricks , sand and aggregates? please my email id is smgujjal@gmail.com
Anyone have sample questions for bhel interview.please send me as Iam appearing for the interview on 19th sep2008. Kindly send this to my e-mail: arun_prasath_n@yahoo.co.in
What is the strength of 1:6:12 mix?
I HAVE APPLIED FOR 20TH UES ARMY. I WANTED TO KNOW WHEN WILL I RECEIVE CALL LETTER FOR THE SAME.
please send me bhel questions on rupesh.017@rediffmail.com
PLS.......... ANY ONE CAN FORWARD ME PREVIOUS QUESTION PAPER hpcl civil engg
Please tell me Detail cost of providing& laying nominal mix design 1:2.5:5,40mm nominal size.curing complete e/c cost of form work in foundation and plinth i/c carriage.