In BoM i mentioned item category as L But when i create po
for sub-contracting defaultly it shows T, I dont understant
where i done mistake, can you help me please by sadeesh
Answer Posted / satish
Hi Siva
BOM ELEMENT DEALS WITH MM; PP and SD modules so it is not
only MM or SD
When you create subcontract the T- CODE to be used is M21N
and the order type is NB the reason why the Item category
changed to T or M instead of L is based on the Typs of
Material you are using . It wil be l if the material is a
not stock material Else will come to the material category
However you need not delete BOM . just change the
material category to NON stock and will get the required
item category
| Is This Answer Correct ? | 4 Yes | 0 No |
Post New Answer View All Answers
Explain lot sizing
What do you understand by posting period?
What is split valuation? What are the settings reuired for it?
How will you consider sub contracting po components which are not sent by your company to vendor but they are added by the vendor (sub contractor)?
What transaction code is used to convert planned orders (po) into requisitions in material requirement planning (mrp)?
How would you convert multiple PRs in POs
Mention what are the types of special stock available?
What is the procedure to delete materials permanently from material master?
What are the different sections in vendor master data?
What are different info records types?
A stock transfer was done between two plants belonging to same company code and between two plants belonging to different company code. What will be the difference between the two?
Why do we use document types in sap?
What is a profit center?
What is a centrally agreed contract?
What is goods movement? What type of documents is created after the goods movement?