what is the sla in your current project? what is the
billing rate? how to answer these questions? i explained
about the ticketing levels p1,p2,p3,p4 but the interviewer
was not satisfied with the answer what does he mean by sla
in the project??
Answer Posted / nbpatil1
Definitions
Incident:
Any event which is not part of the standard operation of a
service and which causes, or may cause, an interruption to,
or a reduction in, the quality of that service.
Ex: Batch Job failures, Users reporting performance issue
Service Request:
A service request is a request for a specific service that
is not due to disruption (i.e. failures in application)
Ex: Request for User id creation, Request for ad-hoc report
Problem:
A proactive ticket initiated in order to find problems
either before they occur or to reduce the overall number of
incidents by proactive measures or provide a permanent fix
to major incidents/outages.
Work-
around:
Method of avoiding an Incident or Problem, either by a
temporary fix or by a technique that means the Customer is
not reliant on a particular aspect of the service that is
known to have a Problem.
Guidelines for Severity
Severity 1(Critical): A critical business process is
hampered. There is
an immediate loss of sales, production, or other comparable
business on a large scale. The affected users have no
readily available alternative way of performing normal work.
Severity 2(High): A critical business process is impaired.
There is an immediate loss of sales, production, or other
comparable business on a medium scale or losses are largely
recoverable. The affected users have no readily available
alternative ways of performing normal work.
Severity 3 (Medium):A non-critical business process is
hampered. There is an immediate loss of sales, production, or
other comparable business on a small scale. The affected users
have readily available alternative ways of performing normal
work.
Severity 4(Low):A non-critical business process is impaired.
There is no immediate loss of sales, production, or other
comparable business. The affected users have readily
available alternative ways of performing normal work.
Bug fix Vs. New functionality(Change Request-CR)
If the business wants a change to current functionality
(i.e. Item Category Mapping), this is definitely a Change
Request. It is not something that worked one way yesterday
and now works a different way today (i.e. Bug Fix Change
Request), but rather something that the business wants to
work differently than it currently does (i.e. Change
Request). Remember something that does not function as
desired, is not a support activity. Only those things that
do not function as designed. Therefore, this is not
something that the support team should be chasing.
| Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
What is a sales deal and how to configure it?
Plant to plant is handled using mb1b. If stock transfer orders with deliveries are configured, use me27.
Does sap transportation management support optimized routing and last mile planning? : transportation management
What is the importance of customer account groups?
How many tickets you have solved till date? can you please elaborate it with solutions?
How to same in period and FY by using Transaction code MMPV
Is it possible to assign two different sales organizations to the same company code?
How is the shipping point determined?
What is “characteristic”? How does the term characteristic relate to transaction code cto4?
Name at least five features that you can control for the schedule line category? Relevance for delivery, availability check, transfer of requirements, goods movement, purchasing and incompletion log.
What table do I use in creating abap program that would output the sales based on sales organization of customers?
What is a 'division'?
What is variant in reporting?
what is a distribution chain ?
What are the various qualifier option or what are the various import options? : transportation management