the amount which paid to contractor before starting work.
what does it calls?
Answer Posted / dheeraj singh
Mobilization advance which will be deducted in running bill
as per norms of Contract, as per prorata basis (complete
recover upto of work completion 80%), we will deduct %of
Givin/80 for example, M.A.-10%, than recoverable
amount=10/80=12.50%
Is This Answer Correct ? | 5 Yes | 0 No |
Post New Answer View All Answers
std penetration resistance in very stiff clays lies bet 2 & 4 4 & 8 8 & 15 15 & 30
What do you mean by bond? What are the different types of bonds?
what is the breaking strength of wall tiles
hi every body..i have applied for RRB section engineers CIVIL.i wanna prepare for that,so can any one suggest me some books and where can i get the syllabus for this..i would be vry greatful if any one can help in this regard
Howmuch bend to be provide for 200/600 BEEM
writte a c prog. to acept 5 no. from consule and then display them back on consulte in ascending order
What is the zero value in quantity surveying
factory shed foundation l=4, b=3' d=8' rcc foudation for top to bottom pl tell me cement ,steel ,sand ,labour cost ,excavtion,soil is weak not so hard
How do you convert wind speed into force?
Explain what is the release of lien?
The concrete slump recommended for beams and slabs; is?
Explain what is 1/8 on the architect ruler denotes?
Why the statue of liberty is made of copper?
How do we calculate absolute pressure?
How many square meter can mason layout chb per hour