calculate multiplication factor of a trivector meter with
line ct ratio 200/5A, line PT ratio 11000/110V and meter CT
ratio 200/1A and meter pt Ratio 11000/110V.

Answer Posted / k.prakashchandra

If the line CT were of 200/1 ratio, the meter would read
correctly. As the ratio is 200/5, for 200 A primary current
the sec current will be 5 A instead of 1.0 .Hence you have
to divide the reading by 5 ,if it is capable of taking 5A.

Is This Answer Correct ?    9 Yes 3 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

i wasted one year for the job after completed my btech what can i say about 1year time in interview

1583


PLZ sent the previous year question paper for GET in NHPC on my EMail id ppshanker@gmail.com

4917


What do you mean by the zone of protection?

610


Why r u using pf panel. what the uses

1487


What are the difference between normal application Transformer and Solar application Transformer?

1223






3 phase Motor will be given 2 phase after 2 to 5 second we given 3rd phase so Motor Run sum-time in forward or sum time run reverse direction. All time phase sequence is not change. Why motor run in reverse direction? Please Explain........

1470


How may I get the maximum current capacity for a particullar size Alluminum or Copper cable if there is compulsion to use?

1438


What are the two segments of nyquist contour.

636


how can we determine size of a cable by knowing the kw or current rating of a load?how can we calculate the resistance box of a slip ring motor?

1313


what are inductive and capacitive voltage transformers.what are their applications

1490


Diagram on interconnectivity of 11kv transformer with RMU (i.e, one incoming and two outgoing or two incoming and one outgoing)

2202


HOW WE CHOOSE EARTH'S POTENTIAL AS ZERO V?

1590


dg earth connect only in the amf panel or not why

1588


A 7 storey building has a floor area of 35,000sq.ft on each storey. On the ground floor 11KV electrical sub-station is to be erected. A load of 3kw for every 400sq.ft (p.f is 0.8) is proposed for each floor. fire pump 7.5hp, water pump 5hp, lift 2 nos, each 10hp and 20shop load of each shop is 5kw. calculate a. load each floor b. total load of building c. L.T feeders for aech floor and from transformer to main. d. distribution diagram e. capacity of sub-station/capacitor bank f. line diagram

2358


What would cause a 240v choke that should give 110v out on a 16w lamp to gradually increase to 160v?

1736