i have a bar of 36 dia in column, what is the lap length?
Answer Posted / mohammed aijaz hussain
The Lap length of the 36 mm diameter steel bar in column
(compression member) is 45d i.e., 45 X 36 mm = 1620 mm. =
1.62 m.
Is This Answer Correct ? | 1 Yes | 4 No |
Post New Answer View All Answers
How much cement,sand,bricks and water needed for 1square metre brick work?
How to calculate carrying capacity of the existing water supply trunkmain
How much does it cost for a R.C.C cover slab of size (450mmX 600mmx 100mm) double rf net given in feets using hand mix concrete?
Where is the worlds longest elevator and how long is it?
Providing and casting in situ cement concrete M-25 of trap/granite/quartzite/gneiss metal for rcc, Providing formwork,Curing the concrete and Complete. what is rate per Cum. and what is rate for M-30 Grade Concrete.
Can anyone suggest how to determine scheduling of reinforcement of floor beams from Staad model,other than clicking each beam respectively 7 noting down the values ?
natucher of concrete &type of concrete?
The properties of concrete HA-30 and how does it differ with M 30 (specify the important characteristics like workability,strength,mix design,slump test value)and what is the standard relating to it
what is moment-curvature relationship in semi rigid connections??
what motivates you to do a good job
Why reinforcement done in shorter span in two way slabs
what is pile and deam foundation
why is M25 and Fe 500 assumed to be most economical? i feel it is not.This is because higher grade of concrete and steel has higher lapping length and anchorage length compared to lower grades..
01. a. Diagram of a slump cone…………… 1 b. Size of Slump Cone…………… 1 c. Volume of a slump cone by av. Dia method…………… 1 d. Volume of a slump cone by av. area method…………… 1 e. Volume of a slump cone by frustrum method …………… 1 f. Angles of slump cone …………… 1 g. Slump measured by slump cone due to…………… 1 h. Slump does not measured by cylinder / cube due to …………… 1 i) ii) i. Slump cone is to be filled in……………………..Layers.
how many shuttering material required for 1000 sq.m built up area.