how many average of shuttering in one cubic meter concrete

Answer Posted / v.kapil

i understand your problem
if you want to calculate shuttering in a genral rasidential
building so you can consider 5-6 Sqm / Cum of conc. but
when you talking about foundation it reduced up to 2-3 Sqm/
Cum, ultimatly there is no as such thumb rule but we can
adopt a value by our experience...

Is This Answer Correct ?    57 Yes 6 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

How can calculate the requirement of steel bars of rcc slab for 1100 sq ft?

1483


1m square 20mm plastering how much of water need curing work

1455


Please Clear My doubt . We Can Design the size of the beam by manually by the Length of the beam...What is the technique adopted

1290


What is the density of most of construction materials?

723


if a pipe those configuration (ASTM c 76 class b 450mm dia 2500mm length) fixing for water course those lining of water is 7000 running meter. my question is that if 8 joints of pipe ls leakage and we have not permission to stop the water so which treatment we apply on joint in that in condition.

1691






what is called the inverd level of mabhole chamber?

1622


by which materials we can prepare circular shuttering with tentative cost of material(rate analysis)

1689


what is Short bored pile foundation.

2191


to draw bm diagrams for portal frames under different loadings//

2436


why the cracks occurs in NP3 class Hume Pipe ? And what is bearing capacity of it?

2751


What is the difference between engineering stress and true stress?

648


Spider cracks occur in beam bottom due to––

1641


sir i want to know that in L & T construction can we do our 6 months training proggramme cum placement???????

1756


please give me the rates of RCC(CUM), PCC(CUM), Brick Work(CUM), Tile Flooring, Saria Shuttering

1055


how to control PQI (Project Quality Index)

9812